  1. Other Activity

Next month Winter 2012

Guide on Reporting Percentage Completed:

For software development tasks:

  • use 0% if the solution is still being designed;
  • use 25% if the solution's design is completed;
  • use 50% if the solution is implemented and tested within the Ticket branch;
  • use 75% if the implementation review is complete, the Ticket branch has been merged onto the Trunk branch, and the Ticket is closed.
  • use 100% if the affected Trunk packages are tagged and released.

For level of effort tasks, use % of effort expended rounded to nearest 5%:

For other tasks, still use these increments, but apply their meaning as best as possible:

  • use 0% if the deliverable is still being designed;
  • use 25% if the deliverable's design is completed;
  • use 50% if the deliverable is implemented awaiting review/approval;
  • use 75% if the deliverable has been reviewed and in revision;
  • use 100% if the deliverable is approved and posted to appropriate repository.

Note: Please place an asterisk (*) after the percent if you updated this value in this report.

Task Start Finish Resources (lead first) % Complete Comments Last Updated
Alert and Calibration Productions 20111004 20111212
ip_isr redesign 20111018 20111031 Krughoff S, Becker A 0% In design phase. Informed by pipette redesign. 20111020
afw pixel classes (region, image, footprint) redesign 20111004 20111107 Lupton R, Owen R, Becker A 0% Initial proposal by JFB waiting in review-scheduling queue. 20111020
afw pixel class reimplementation 20111108 20111212 Lupton R, Owen R, Becker A 0% 20111024
Data Release Production and Application Framework 20110901 20120116
Measurement infrastructure rework (#1760) 20110901 20111109 Price P 0%
Port stack to new third party packages (#1782, #1752; does not include SWIG 2) 20111004 20111031 Bosch J 30% Ready on branch through afw; working on distribution server. 20111020
Port stack to SWIG 2 20111004 20111031 Monkewitz S 0%
Remove daf_data, sdqa, security 20111004 20111031 Bosch J 40% daf_data, security removed in branch. 20111020
Apps package reorganization 20111011 20111031 Bosch J 20% Waiting on final review (seems popular, but no official decision yet) and implementation scheduling. 20111020
Source redesign 20111108 20111205 Lupton R, Price P, Lang D, Lim K-T 0%
Source reimplementation 20111206 20120116 Price P, Lang D, Lim K-T, Lupton R 0%
Processing Middleware and Archive Site 20110901 20120116
Build environment, tagging, preparation 20110901 20110909 Plante R, Gehrig D 50% Actively in progress. Completed deployment of 4.5 series of packages. Third party packages migrated to new stack based on updated eups and sconsUtils. 20111025
Upgrade eups/sconsUtils and third party packages 20110912 20111017 Plante R 100% Done; available in test server 20111025
Move all machines to RHEL6 20110912 20111017 Freemon M, Daues G, Pietrowicz S 50% Weekly-type run using final PT1.2 tags executed successfully across lsst9/lsst14/lsst15. Internal NCSA testing complete. Currently being tested by DM developers. Current state: Waiting for consensus/approval from the DM developers before upgrading lsst[5,11,6,8]. 20111021
Write package release tool 20110912 20111024 Plante R 25% work on the scripts have been started; however, emphasis has been put on putting up useable servers to support developers 20111025
Pipette/butler/policy redesign 20110912 20111024 Owen R, Dubcovsky M, Lim K-T 0% Redesign of pipette is ready for review--R Owen 20111024
sconsUtils/package layout transition (#1780) 20111004 20111024 Bosch J 40% sconsUtils and low-level packages complete in branch. 20111020
git/hg evaluation/decision 20111004 20111024 Price P, Lang D, Juric M, Lupton R 20% Consensus to abandon svn. Git information collected at GitProposalMJuric 20111020
buildbot automation and automation of weekly/triggered runs 20111011 20111024 Gehrig D, Lim K-T, Pietrowicz S 60% Cleanup continues. New scripts being tested. Working on transistioning to new RHEL6 buildbot slaves. 20111020
git/hg transition 20111025 20111107 Gehrig D, Freemon M 0%
Pipette/butler/policy implementation 20111025 20111121 Owen R, Dubcovsky M, Lim K-T 0% 20111024
Develop stripped-down prototype pipeline for middleware R&D 20111101 20111121 Daues G, Pietrowicz S, Lim K-T 0%
Implement prtotype pipeline on NHPPS ( doc) 20111122 20111219 Daues G, Pietrowicz S 0% AstroWise documentation under examination; NHPPS source is being studied 20111021
Implement prototype pipeline on OWL or Condor 20111220 20120116 Daues G, Pietrowicz S 0%
Data Management System Integration and Test 20120117 20120227
Winter 2012 Production Runs 20120117 20120213 Daues G, Pietrowicz S, Lim K-T, Gehrig D, Allsman R 0%
Winter 2012 Data Analysis - LSST 20120131 20120227 Juric M, Axelrod T, Shaw D, Lupton R, Becker A, Lim K-T, Science Collaborations 0%

Other Activity