Status Report for February 15, 2009



Summary of progress

Work activity; whether it reached associated milestones.

NCSA

Bill (submitted on 2/xx/2009)

Chris (submitted on 2/xx/2009)

David (submitted on 2/xx/2009)

Greg (submitted on 2/xx/2009)

Steve (submitted on 2/xx/2009)

Mike (submitted on 2/xx/2009)

Ray (submitted on 2/xx/2009)


LSSTC

Robyn (submitted on 2/13/2009)

Note: Only my tasks, not listed on the most recent Project Schedule as 100% completed, are included.

Status NL Not Lead
Status NW No work done
Id PM Project Management Plan
Id DC Data Challenge Plan
Id AP Applications Plan
Id MW Middleware Plan


.Status.Id...........Title.........................Comment..............
NL NW PM50 ...Update SysML/UML models and prepare Technical Documents
NL NW PM51 ......Complete LSST Software Development Plan Waiting on Review
NL NW PM51 .........LSST Software Development Plan
NL NW PM52 .........LSST Configuration Management Guidelines
NL NW PM53 .........LSST Software Quality Assurance Guidelines
NL NW PM54 .........LSST Verification and Validation Guidelines
NL NW PM60 ...Complete DM Inputs to System Level Requirements and Design
NL NW PM67 ......Create document templates, recipes, tools for Enterprise Architect output/gen
NL NW PM68 ...Complete Data Management Reference Design
NL NW PM69 ......Clean up DC3 UML Model, Update LSST Reference Design UML Model
NL NW PM70 ......Update EA and UML Modeling Conventions Document for Activity Diagrams
PM75 ...Create draft DM Integration Test Plan
0% PM77 ......Generate test cases Need TestGen? update
NL NW PM78 Complete PM Control System Updates
NL NW PM81 ...Publish cost book, do team review
NL NW PM85 ...Conduct PM Internal Cost Review and updates
NL NW PM86 Complete DM Inputs to Risk Management, System Integration, Commissioning, and Operations Plans
0% PM87 ...Update DMS Integration and Test Plan
PM90 ...Contribute DM sections to LSST Risk Management, Commissioning, I&T, and Operations Plans
DC56 Data Challenge 3 Software Development Plan
100% DC57 ...DC3 Release Project Plan
50% DC58 ...DC3 Configuration Management Plan Need feedback from Gehrig, Daues, Plante
100% DC59 ...DC3 Software Quality Assurance Plan
DC60 ...DC3 Verification and Validation Plan
75% ......DC3a Verification and Validation Plan Close but some sections missing
0% ......DC3b Verification and Validation Plan
100% MW6 Software Quality Assurance
100% MW7 ...Acquire SQA Support tools
100% MW8 ......Configurable tool to perform Lsst software standards checking
100% MW9 .........C++ LSST benchmark test suite packaged
100% MW10 .........Benchmark
MW11 superfluous - drop from plan
MW12 superfluous - drop from plan
MW13 superfluous - drop from plan
100% MW14 .........Acquire
100% MW15 ......Coverage Analysis Tool
100% MW16 .........Benchmark
100% MW17 .........Release for developer use
100% MW18 ...Refine workflow process to incorporate additional V&V...

Database Group (submitted on 2/xx/2009)

K-T (submitted on 2/xx/2009)

Andy H (submitted on 2/xx/2009)

Serge (submitted on 2/xx/2009)

Jacek (submitted on 2/xx/2009)



Major Accomplishments

Significant breakthroughs, issues resolved.



Objectives for the Next Period

What you expect to accomplish.

NCSA

  • Bill:
  • Chris:

  • David:
  • Steve:

  • Greg:

  • Mike:
  • Ray:


LSSTC

  • Robyn:
    • Complete the DC3a Integration Test Plan
    • Ensure misc input needed for Integration Test are available prior to Integration Week.
    • Cajole pipeline developers to implement single slice pipeline test harness for their pipeline.


Database Group



Problems Encountered and Solutions Being Pursued

Budget or schedule variance, technical issues, management issues

  • Robyn is nudging the cross-group preparation of the CFHT and simulated LSST datasets for DC3a use.