  • PT1_1Report20110115

    v11 v12  
    3434|| ''Production-Pipeline-Stage Middleware'' || || || ''Pietrowicz Steve'' || || || || 
    3535|| Improve Logging performance, reporting, error checking || 8/23/10 || 11/2/10 || Pietrowicz Steve[10%],Daues Greg[10%] || 100% || Done with PT1.1 runs. || Mon 1/24/11 || 
    36 || Improve shutdown mechanism for data stack || 11/3/10 || 11/3/10 || Daues Greg[10%],Pietrowicz Steve[35%] || 25% || Solution designed and being worked on for weekly runs || Mon 2/22/11 || 
     36|| Improve shutdown mechanism for data stack || 11/3/10 || 11/3/10 || Daues Greg[10%],Pietrowicz Steve[35%] || 25% || Solution designed and being worked on for weekly runs || 2/22/11 || 
    3737|| Complete JobOffice implementation to allow integration of Source Association || 9/2/10 || 10/22/10 || Plante Ray[50%] || 100% || This capability was integrated; however, it was not used in PT1.1.(due to Source Association constraints); thus, I can't claim it is fully validated. || 01/25/11 || 
    3838|| Automate transfer of data to/from MSS for staging/storing results of a production tool || 9/9/10 || 10/26/10 || Plante Ray[10%],Adams Darren || 100% || sufficient capability in 1.1, more automated in 1.2 || 01/26/11 ||