Guide on Reporting Percentage Completed:

For software development tasks:

  • use 0% if the solution is still being designed;
  • use 25% if the solution's design is completed;
  • use 50% if the solution is implemented and tested within the Ticket branch;
  • use 75% if the implementation review is complete, the Ticket branch has been merged onto the Trunk branch, and the Ticket is closed.
  • use 100% if the affected Trunk packages are tagged and released.

For level of effort tasks, use % of effort expended rounded to nearest 5%:

For other tasks, still use these increments, but apply their meaning as best as possible:

  • use 0% if the deliverable is still being designed;
  • use 25% if the deliverable's design is completed;
  • use 50% if the deliverable is implemented awaiting review/approval;
  • use 75% if the deliverable has been reviewed and in revision;
  • use 100% if the deliverable is approved and posted to appropriate repository.

Note: Please place an asterisk (*) after the percent if you updated this value in this report.

Task Start Finish Resources (lead first) % Complete Comments Last Updated
Environment and Tools Plante Ray
ImSim Data Krughoff Simon 11/17/2010
Import reference catalogs into Gator for comparison to output catalogs 11/3/10 11/4/10 Monkewitz Serge[50%] 0% NA
Production-Pipeline-Stage Middleware Pietrowicz Steve
Improve Logging performance, reporting, error checking 8/23/10 11/2/10 Pietrowicz Steve[10%],Daues Greg[10%] 75% Runs continue to be executed; new Event Broker configuration prevents events from being stalled at the event producer; additional calculations added to duration scripts; Log statements with CPU time, Sys time, Wall time implemented. Fri 12/10/10
Improve shutdown mechanism for data stack 11/3/10 11/3/10 Daues Greg[10%],Pietrowicz Steve[35%] 0% Not required for production runs. NA
Complete JobOffice? implementation to allow integration of Source Association 9/2/10 10/22/10 Plante Ray[50%] 50% Implementation is completed; includes unit tests; need to complete integration tests Tue 10/12/10
Automate transfer of data to/from MSS for staging/storing results of a production tool 9/9/10 10/26/10 Plante Ray[10%],Adams Darren 75% Limited capability in 1.1, more extensive in 1.2 Tue 10/12/10
Data Release Production Architecture and Performance Lim KT
Data Access Middleware and Database Lim KT
Pass through comments in FITS headers 10/20/10 11/2/10 Lim KT[25%] 0% Some design done, unclear if this will make PT1.1. Requires changes to afw, exposure, persistence of them. Also would implement preserving header order with this. Sun 10/10/10
Persist image characterization matches against reference catalog 10/25/10 11/1/10 Lang Dustin, Lim KT 25% 10/25/10
Point Source Photometry Lupton Robert
Implement photometry/astrometry flag 10/20/10 11/2/10 Lang Dustin[50%] 0% NA
Implement aperture corrections 8/23/10 10/26/10 Bickerton Steve[50%] 50% Mon 10/18/10
Galaxy Photometry Bosch Jim 10/24/2010
Determine fitting code failure modes 8/23/10 10/29/10 Bosch Jim[10%],Dubcovsky Martin[50%] 90% Testing on individual CCDs, characterizing failures (progress is essentially open-ended). Wed 11/10/2010
Determine fitting outputs to be stored in database 10/28/10 10/29/10 Bosch Jim[10%],Dubcovsky Martin[50%] 100% Determining additional flags for modeling failures. Sun 10/24/2010
Update Source class for galaxy photometry, incl formatters 9/6/10 11/1/10 Monkewitz Serge[50%],Lupton Robert[50%] 25% New meas::algorithms should support this, needs to be confirmed Tue 10/12/10
Source Association Serge Monkewitz
Define SDQA metrics for Source Association 8/23/10 10/22/10 Monkewitz Serge[50%],Axelrod Tim[25%] 75% initial metrics defined Tue 11/02/10
Implement SDQA metrics for Source Association 8/26/10 11/2/10 Monkewitz Serge[50%] 90% ref to object catalog matching and ref to science ccd filtering code complete. Tue 11/02/10
Change Source Association to use inverse variance weighting and calibrated fluxes 11/2/10 11/4/10 Monkewitz Serge[50%] 90% Code still needs to be reviewed by Tim NA
Build and Test Allsman Robyn 11/1/10
Monitor buildbot integration and test 9/6/10 10/29/10 Allsman Robyn[25%] 80% The buildbot slave has been upgraded to gcc 4.4 and the OS has been changed to FedoraCore to bring buildbot into alignment with the development software environment. Only the trunk continuous integration buildbot has been installed. The other varients will be cloned and installed after the new year. 12/27/10
Production Runs Daues Greg
App debug/practice runs on lsst with ImSim data 10/20/10 11/2/10 Daues Greg[10%] 0% NA
Abe runs with ImSim data subsets 11/5/10 11/18/10 Daues Greg[50%] 15% A practice run has processed Imsim visit v85661762-fr (189 CCDs) using the 4.1.0.x software stack with no reported errors/exceptions. A 6-visit run will be initiated after Apps updates in response to the 1-visit run are complete. Want to freeze stack on 11/1/10, will do a series of runs between now and then. Want 3-day turn-around on fixes. Fri 10/15/10
User Support Shaw Dick
Prepare Data Challenge Handbook 8/23/10 11/2/10 Shaw Dick[50%] 90%* Technical review is underway for all content except Ch. 5 (on data quality). A further update is planned for 29-Dec to incorporate feedback on technical issues. A final update on 5 Jan will incorporate feedback from external reviewers. 12/27/10
Organize DM User Support 9/20/10 11/9/10 Shaw Dick[50%] 80%* Most User Support issues resolved, except HelpDesk e-mail list needs to be established. Planning for AAS splinter session on PT1.1 data access is underway, with draft PPT slides planned for ~3 Jan. 12/27/10
Configure/tune catalogs 11/10/10 11/23/10 Becla Jacek[10%] 75% Minor schema tweaks. 01/03/11
Data Analysis Axelrod Tim
DM Scientist/Engineer? data analysis 10/20/10 11/2/10 Axelrod Tim[50%],Lupton Robert[50%],Bosch Jim[50%],Becker Andy[50%],Van Dyk Schuyler[25%],Shaw Dick[50%] ACB:50% ACB:Completed unified pipeline runs on phot test data; currently comparing to input catalogs. Results: completeness to 23rd magnitude; PSF flux uncertainties need to have 1.2% added in quadrature on the bright end to be commensurtae with scatter; photometry repeatibility to 1.5% on bright end. Analysis of images run through zeropointing pipeline shows significantly worse results (0.5 mag scatter on bright end). 12/10/10
Science Collaboration data analysis 11/10/10 12/7/10 Science Collaboration 0% NA
Data analysis report 12/1/10 12/7/10 Axelrod Tim[50%],Lupton Robert[50%],Bosch Jim[50%],Becker Andy[50%],Van Dyk Schuyler[25%],Shaw Dick[50%],Science Collaboration 0% NA