Guide on Reporting Percentage Completed:
For software development tasks:
- use 0% if the solution is still being designed;
- use 25% if the solution's design is completed;
- use 50% if the solution is implemented and tested within the Ticket branch;
- use 75% if the implementation review is complete, the Ticket branch has been merged onto the Trunk branch, and the Ticket is closed.
- use 100% if the affected Trunk packages are tagged and released.
For level of effort tasks, use % of effort expended rounded to nearest 5%:
For other tasks, still use these increments, but apply their meaning as best as possible:
- use 0% if the deliverable is still being designed;
- use 25% if the deliverable's design is completed;
- use 50% if the deliverable is implemented awaiting review/approval;
- use 75% if the deliverable has been reviewed and in revision;
- use 100% if the deliverable is approved and posted to appropriate repository.
Note: Please place an asterisk (*) after the percent if you updated this value in this report.
Task | Start | Finish | Resources (lead first) | % Complete | Comments | Last Updated |
Environment and Tools | Plante Ray | |||||
Support trac, svn, systems administration | 8/30/10 | 11/1/10 | Pietrowicz Steve[15%] | 80% | Fri 10/15/10 | |
ImSim Data | Krughoff Simon | |||||
Create ImSim Data Flow for PT 1.1 from all image generation sites | 9/1/10 | 10/22/10 | Plante Ray[25%],Krughoff Simon[25%] | 50% | SK: Fields selected, staging script set up.; RP: scripts received; in final testing | Tue 10/12/10 |
Generate reference star galaxy catalogs (turn on magnitudes, w/improved photometry) | 9/20/10 | 11/2/10 | Krughoff Simon[30%],Gibson Rob | 50% | Star catalog generation complete, bug: all stars are flagged as variable, even those that are static (not show-stopper). Galaxy generation complete to r < 23, sufficient. Reformatting for shipment to Serge M. in progress. | Tue 10/19/10 |
Import reference catalogs into Gator for comparison to output catalogs | 11/3/10 | 11/4/10 | Monkewitz Serge[50%] | 0% | NA | |
Production-Pipeline-Stage Middleware | Pietrowicz Steve | |||||
Improve Logging performance, reporting, error checking | 8/23/10 | 11/2/10 | Pietrowicz Steve[10%],Daues Greg[10%] | 50% | Updated in trunk, additional testing happening now; The harness issues log statements with CPU time, Sys time, Wall time for visits (tag 4.1.0.0) | Mon 10/11/10 |
Update Event Monitor for execution statistics | 9/6/10 | 11/2/10 | Pietrowicz Steve[15%] | 50% | Updated, but additional testing required | Mon 10/11/10 |
Improve shutdown mechanism for data stack | 11/3/10 | 11/3/10 | Daues Greg[10%],Pietrowicz Steve[35%] | 0% | Not required for production runs. | NA |
Complete JobOffice? implementation to allow integration of Source Association | 9/2/10 | 10/22/10 | Plante Ray[50%] | 50% | Implementation is completed; includes unit tests; need to complete integration tests | Tue 10/12/10 |
Automate transfer of data to/from MSS for staging/storing results of a production tool | 9/9/10 | 10/26/10 | Plante Ray[10%],Adams Darren | 75% | Limited capability in 1.1, more extensive in 1.2 | Tue 10/12/10 |
Data Release Production Architecture and Performance | Lim KT | |||||
Data Access Middleware and Database | Lim KT | |||||
Pass through comments in FITS headers | 10/20/10 | 11/2/10 | Lim KT[25%] | 0% | Some design done, unclear if this will make PT1.1. Requires changes to afw, exposure, persistence of them. Also would implement preserving header order with this. | Sun 10/10/10 |
Persist image characterization matches against reference catalog | 10/25/10 | 11/1/10 | Lang Dustin, Lim KT | 25% | 10/25/10 | |
Point Source Photometry | Lupton Robert | |||||
Implement photometry/astrometry flag | 10/20/10 | 11/2/10 | Lang Dustin[50%] | 0% | NA | |
Implement aperture corrections | 8/23/10 | 10/26/10 | Bickerton Steve[50%] | 50% | Mon 10/18/10 | |
Galaxy Photometry | Bosch Jim | 10/24/2010 | ||||
Determine fitting code failure modes | 8/23/10 | 10/29/10 | Bosch Jim[10%],Dubcovsky Martin[50%] | 50% | Testing on individual CCDs, characterizing failures (progress is essentially open-ended). | Sun 10/24/2010 |
Determine fitting outputs to be stored in database | 10/28/10 | 10/29/10 | Bosch Jim[10%],Dubcovsky Martin[50%] | 90% | Determining additional flags for modeling failures. | Sun 10/24/2010 |
Update Source class for galaxy photometry, incl formatters | 9/6/10 | 11/1/10 | Monkewitz Serge[50%],Lupton Robert[50%] | 25% | New meas::algorithms should support this, needs to be confirmed | Tue 10/12/10 |
Source Association | Serge Monkewitz | |||||
Define SDQA metrics for Source Association | 8/23/10 | 10/22/10 | Monkewitz Serge[50%],Axelrod Tim[25%] | 25% | initial proposal sent to Tim | Fri 8/27/10 |
Implement SDQA metrics for Source Association | 8/26/10 | 11/2/10 | Monkewitz Serge[50%] | 25% | Implemented coverage map generation (for determining the expected maximum number of sources for an object at a given position). Began implementing reference to output object catalog cross-matching - so far, I've got code that filters the reference catalog | Thu 9/16/10 |
Change Source Association to use inverse variance weighting and calibrated fluxes | 11/2/10 | 11/4/10 | Monkewitz Serge[50%] | 0% | NA | |
Build and Test | Allsman Robyn | 11/1/10 | ||||
Monitor buildbot integration and test | 9/6/10 | 10/29/10 | Allsman Robyn[25%] | 80% | Upgrading slaves to use gcc 4.4 to bring into alignment with development software environment; simplified buildbot waterfall web page | Mon 11/1/10 |
Production Runs | Daues Greg | |||||
App debug/practice runs on lsst with ImSim data | 10/20/10 | 11/2/10 | Daues Greg[10%] | 0% | NA | |
Abe runs with ImSim data subsets | 11/5/10 | 11/18/10 | Daues Greg[50%] | 15% | A practice run has processed Imsim visit v85661762-fr (189 CCDs) using the 4.1.0.x software stack with no reported errors/exceptions. A 6-visit run will be initiated after Apps updates in response to the 1-visit run are complete. Want to freeze stack on 11/1/10, will do a series of runs between now and then. Want 3-day turn-around on fixes. | Fri 10/15/10 |
User Support | Shaw Dick | |||||
Prepare Data Challenge Handbook | 8/23/10 | 11/2/10 | Shaw Dick[50%] | 60% | Awaiting requested input on details of processing algorithms. Awaiting bug fix to public data access mechanism, so that testing and documentation can be finalized. Sent DCH to M.Strauss for editorial review. Technical review now planned for 5-Nov. | 11/1/10 |
Organize DM User Support | 9/20/10 | 11/9/10 | Shaw Dick[50%] | 60% | Most User Support issues resolved, except HelpDesk software and installation of User Forum software. Planning for pre-AAS session on PT1.1 data access is underway. | 11/1/10 |
Configure/tune catalogs | 11/10/10 | 11/23/10 | Becla Jacek[10%] | 0% | NA | |
Data Analysis | Axelrod Tim | |||||
DM Scientist/Engineer? data analysis | 10/20/10 | 11/2/10 | Axelrod Tim[50%],Lupton Robert[50%],Bosch Jim[50%],Becker Andy[50%],Van Dyk Schuyler[25%],Shaw Dick[50%] | ACB:50% | ACB:Completed unified pipeline runs on phot test data; currently comparing to input catalogs. | 11/1/10 |
Science Collaboration data analysis | 11/10/10 | 12/7/10 | Science Collaboration | 0% | NA | |
Data analysis report | 12/1/10 | 12/7/10 | Axelrod Tim[50%],Lupton Robert[50%],Bosch Jim[50%],Becker Andy[50%],Van Dyk Schuyler[25%],Shaw Dick[50%],Science Collaboration | 0% | NA |