    Guide on Reporting Percentage Completed:

    For software development tasks,

    • use 0% if the solution is still being designed;
    • use 25% if the solution's design is completed;
    • use 50% if the solution is implemented and tested within the Ticket branch;
    • use 75% if the implementation review is complete, the Ticket branch has been merged onto the Trunk branch, and the Ticket is closed.
    • use 100% if the affected Trunk packages are tagged and released.

    For other tasks, still use these increments, but apply their meaning as best as possible.

    Note: Please place an asterisk (*) after the percent if you updated this value in this report.

    Middleware/Infrastructure? Status Report for September 15, 2010

    Major Accomplishments

    Significant breakthroughs, issues resolved.



    Objectives for the Next Period

    What you expect to accomplish.



    Problems Encountered and Solutions Being Pursued

    Budget or schedule variance, technical issues, management issues.