wiki:MSEReport20110915

Version 12 (modified by jkantor, 8 years ago) (diff)

--

Table of Contents

  1. Other Activity

Previous month PT1.2 - Mgt/SE

Next month : Winter12 status reporting will be done via trac tickets, and MSE will be planned and statused via PMCS starting in October, 2011

Note: Please place an asterisk (*) after the percent if you updated this value in this report. Also, please update the "Last Updated" column even if the % complete hasn't changed; that way we'll know that the figure represents the most current information.

Note: Critical? refers to level of need for Preliminary Design Review: XX = Must complete, X = Valuable to complete but already good enough, Blank = Nice to have.

Task Critical? Start Finish Resources (lead first) % Complete Comments Last Updated
Pipeline Execution Middleware Scaling Tests KT Lim, Ray Plante
Define scaling tests 20110222 20110606 Plante Ray[5%] 50% 20110426
Create benchmark stage implementations and pipeline configurations 20110606 20110627 Daues Greg[25%] 0% 20110426
Execute scaling tests, analzye, report results 20110627 20110718 Daues Greg[25%] 0% 20110426
MOPS Analyses Tim Axelrod
Complete analysis of runs of FindTracklets/LinkTracklets and OrbFit driven by simulated DIASources 20081010 20110613 Axelrod Tim[20%],Myers Jonathan[75%] 75% 20110922
Estimate amount of CPU required for LSST MOPS 20101108 20110615 Axelrod Tim[20%],Myers Jonathan[75%] 75% 20110922
Prototype key algorithms in MOPS design 20101206 20110706 Axelrod Tim[20%],Myers Jonathan[75%] 75%* 20110922
Determine requirements for FutureMOPS that will satisfy solar system science requirements as sketched out in SRD 20110117 20110713 Axelrod Tim[20%],Myers Jonathan[75%] 50% 20110922
Update Structure Model Gregory Dubois-Felsmann
Create DM internal ICD N2 diagram 20110603 20110603 Dubois-Felsmann Gregory[50%] 0%
Update Structure Model - FRS traceability 20110711 20110713 Dubois-Felsmann Gregory[50%] 0%
Prepare ICDs Gregory Dubois-Felsmann
DM-CCS 20110103 20110627 Dubois-Felsmann Gregory[25%],Marshall Stuart[25%] 50%* 20110829
DM-TCS 20110309 20110630 Sebag Jacques[50%],Dubois-Felsmann Gregory[50%] 50%* 20110829
DM-OCS 20110317 20110708 Dubois-Felsmann Gregory[50%],Schumacher German[50%] 50%* 20110829
DM-EPO 20110602 20110616 Jacoby Suzanne[50%],Dubois-Felsmann Gregory[20%] 50%* 20110829
DM-sites 20110516 20110621 Dubois-Felsmann Gregory[50%],Lambert Ron[50%],Barr Jeff[50%] 50%* 20110829
Update App and MW Reference Design for DC3a, DC3b PT1, PT1.1 Gregory Dubois-Felsmann
Update reference design - structure model traceability 20110617 20110621 Dubois-Felsmann Gregory[50%],Kantor Jeff[25%],Allsman Robyn[50%],Lim KT[25%],Plante Ray[25%] 0% 20110621
Requirements and Design for Science User Interface Schuyler Van Dyk
Integrate into FRS and prepare system requirements change requests to integrate 20110609 20110622 Van Dyk Schuyler[5%],Dubois-Felsmann Gregory[25%],Levine Deborah[5%] 0% 20110920
Create sample use cases, domain model 20110706 20110707 Levine Deborah[50%],Rosenberg Doug [25%] 25%* 20110920
Collate existing (best-of-breed) technology options with requirements 20110418 20110622 Van Dyk Schuyler[50%],Dubois-Felsmann Gregory[5%],Levine Deborah[50%] 50%* 20110920
Review with SAT, update and re-baseline 20110623 20110706 Van Dyk Schuyler[50%],Dubois-Felsmann Gregory[50%],Levine Deborah[50%] 0% 20110920
DM Test Plans Robyn Allsman No Change 20110920
Draft DM Unit Test documents 20100930 20110707 Allsman Robyn[25%] 50% Updated SDP's DM V&V section to include test implementation responsibility during DC and Construction. NOT YET APPROVED by TCT/SAT/etc. 20110520
Draft DM Integration Test documents 20101014 20110714 Allsman Robyn[25%] 50% Draft is outlined and 75% fleshed out. 20110520
Draft DM System Test documents 20110715 20110719 Allsman Robyn[35%] 0% 20110520
Draft DM Acceptance Test documents X 20110720 20110726 Allsman Robyn[25%] 0% 20110520
Generate Integration Test Cases from DM Ref Design Use Cases/Activities? 20110519 20110728 Allsman Robyn[50%] 75% 20110520
Create Performance System Test Cases from DM Subsystem Requirements Constraint Blocks 20110728 20110804 Allsman Robyn[50%] 0% 20110520
Generate Functional Acceptance Test Cases from DM Subsystem Requirements 20110804 20110811 Allsman Robyn[50%] 0% 20110520

Other Activity