Changes between Version 12 and Version 13 of MSEReport20110915


Ignore:
Timestamp:
09/22/2011 02:59:47 PM (8 years ago)
Author:
ktl
Comment:

Updated KTL and GPDF tasks.

Legend:

Unmodified
Added
Removed
Modified
  • MSEReport20110915

    v12 v13  
    1010 
    1111|| '''Task''' || '''Critical?''' || '''Start''' || '''Finish''' || '''Resources (lead first)''' || '''% Complete''' || '''Comments''' || '''Last Updated''' || 
    12 || ''Pipeline Execution Middleware Scaling Tests'' || || || || ''KT Lim, Ray Plante'' || || || || 
     12|| ''Pipeline Execution Middleware Scaling Tests'' || || || || ''KT Lim, Ray Plante'' || || Some numbers were captured during PT1.2 runs and should be included in the report.  Dedicated scaling tests are anticipated for later in Winter2012. || || 
    1313|| Define scaling tests || || 20110222 || 20110606 || Plante Ray[5%] || 50% ||  || 20110426 || 
    1414|| Create benchmark stage implementations and pipeline configurations || || 20110606 || 20110627 || Daues Greg[25%] || 0% ||  || 20110426 || 
     
    1919|| Prototype key algorithms in MOPS design || || 20101206 || 20110706 || Axelrod Tim[20%],Myers Jonathan[75%] || 75%* ||  || 20110922 || 
    2020|| Determine requirements for FutureMOPS that will satisfy solar system science requirements as sketched out in SRD || || 20110117 || 20110713 || Axelrod Tim[20%],Myers Jonathan[75%] || 50% ||  || 20110922 || 
    21 || ''Update Structure Model'' || || || || ''Gregory Dubois-Felsmann'' || || || || 
    22 || Create DM internal ICD N2 diagram || || 20110603 || 20110603 || Dubois-Felsmann Gregory[50%] || 0% ||  || || 
    23 || Update Structure Model - FRS traceability || || 20110711 || 20110713 || Dubois-Felsmann Gregory[50%] || 0% ||  || || 
    24 || ''Prepare ICDs'' || || || || ''Gregory Dubois-Felsmann'' || || || || 
    25 || DM-CCS || || 20110103 || 20110627 || Dubois-Felsmann Gregory[25%],Marshall Stuart[25%] || 50%* ||  || 20110829 || 
    26 || DM-TCS || || 20110309 || 20110630 || Sebag Jacques[50%],Dubois-Felsmann Gregory[50%] || 50%* ||  || 20110829 || 
    27 || DM-OCS || || 20110317 || 20110708 || Dubois-Felsmann Gregory[50%],Schumacher German[50%] || 50%* ||  || 20110829 || 
    28 || DM-EPO || || 20110602 || 20110616 || Jacoby Suzanne[50%],Dubois-Felsmann Gregory[20%] || 50%* ||  || 20110829 || 
    29 || DM-sites || || 20110516 || 20110621 || Dubois-Felsmann Gregory[50%],Lambert Ron[50%],Barr Jeff[50%] || 50%* ||  || 20110829 || 
    30 || ''Update App and MW Reference Design for DC3a, DC3b PT1, PT1.1'' || || || || ''Gregory Dubois-Felsmann'' || || || || 
    31 || Update reference design - structure model traceability || || 20110617 || 20110621 || Dubois-Felsmann Gregory[50%],Kantor Jeff[25%],Allsman Robyn[50%],Lim KT[25%],Plante Ray[25%] || 0% ||  || 20110621 || 
     21|| ''Update Structure Model'' || || || || ''K-T Lim'' || || || || 
     22|| Create DM internal ICD N2 diagram || || 20111017 || 20111107 || Lim K-T[50%] || 0% || I think I saw an early draft of this, but I'll probably need to start almost from scratch || 20110922 || 
     23|| Update Structure Model - FRS traceability || || 2011???? || 2011???? || Lim, K-T[50%] || 0% || I may put this off until Gregory comes back || 20110922 || 
     24|| ''Prepare ICDs'' || || || || ''K-T Lim, Gregory Dubois-Felsmann'' || || || || 
     25|| DM-CCS || || 20110103 || 20111024 || Lim K-T[25%],Marshall Stuart[25%] || 50% || I've taken this over and will complete it for the camera CD-1 review || 20110922 || 
     26|| DM-TCS || || 20110309 || 20110630 || Sebag Jacques[50%],Dubois-Felsmann Gregory[50%] || 50% ||  || 20110922 || 
     27|| DM-OCS || || 20110317 || 20110708 || Dubois-Felsmann Gregory[50%],Schumacher German[50%] || 50% ||  || 20110922 || 
     28|| DM-EPO || || 20110602 || 20110616 || Jacoby Suzanne[50%],Dubois-Felsmann Gregory[20%] || 50% ||  || 20110922 || 
     29|| DM-sites || || 20110516 || 20110621 || Dubois-Felsmann Gregory[50%],Lambert Ron[50%],Barr Jeff[50%] || 50% ||  || 20110922 || 
     30|| ''Update App and MW Reference Design for DC3a, DC3b PT1, PT1.1'' || || || || ''K-T Lim'' || || The UML was substantially improved for PDR, but additional changes to it and to the WBS would be desirable || || 
     31|| Update reference design - structure model traceability || || 20110617 || 20110621 || Dubois-Felsmann Gregory[50%],Kantor Jeff[25%],Allsman Robyn[50%],Lim KT[25%],Plante Ray[25%] || 0% ||  || 20110922 || 
    3232|| ''Requirements and Design for Science User Interface'' || || || || ''Schuyler Van Dyk'' || || || || 
    3333|| Integrate into FRS and prepare system requirements change requests to integrate || || 20110609 || 20110622 || Van Dyk Schuyler[5%],Dubois-Felsmann Gregory[25%],Levine Deborah[5%] || 0% || || 20110920 || 
    3434|| Create sample use cases, domain model || || 20110706 || 20110707 || Levine Deborah[50%],Rosenberg Doug [25%] || 25%* || || 20110920 || 
    3535|| Collate existing (best-of-breed) technology options with requirements || || 20110418 || 20110622 || Van Dyk Schuyler[50%],Dubois-Felsmann Gregory[5%],Levine Deborah[50%] || 50%* || || 20110920 || 
    36 || Review with SAT, update and re-baseline || || 20110623 || 20110706 || Van Dyk Schuyler[50%],Dubois-Felsmann Gregory[50%],Levine Deborah[50%] || 0% || || 20110920 || 
     36|| Review with SAT, update and re-baseline || || 20110623 || 20110706 || Van Dyk Schuyler[50%],Lim K-T[50%],Levine Deborah[50%] || 0% || || 20110920 || 
    3737|| ''DM Test Plans'' || || || || ''Robyn Allsman'' || ||No Change ||20110920 || 
    3838|| Draft DM Unit Test documents || || 20100930 || 20110707 || Allsman Robyn[25%] || 50% || Updated SDP's DM V&V section to include test implementation responsibility during DC and Construction. NOT YET APPROVED by TCT/SAT/etc.  || 20110520 ||