    v22 v23  
    8989|| Consolidate and update Computing workbook and explanation document || 20110222 || 20110420 || Lim KT[20%] || 50% || Consolidation complete; quantities and formulas need review || 20110422 || 
    9090|| Consolidate and update I/O and Storage workbook and explanation document || 20110222 || 20110531 || Lim KT[10%],Becla Jacek[25%],Axelrod Tim[10%] || 80%* || Incorporated and redid network estimates, redid the query access cost model, started documenting storage/io/network spreadsheet. || 20110516 || 
    91 || Update Network workbook and explanation document, integrate into sizing model sheets || 20110222 || 20110421 || Lambert Ron[20%],Kantor Jeff[10%] || 30% || Updated with REUNA being paid in MREFC phase.  In discussion with AmLight for similar for SCL - MIA. || 20110422 || 
     91|| Update Network workbook and explanation document, integrate into sizing model sheets || 20110222 || 20110421 || Lambert Ron[20%],Kantor Jeff[10%] || 75%* || Preparing letters from AmLight, REUNA || 20110422 || 
    9292|| ''Complete DM Inputs to Risk Management, System Integration, Commissioning, and Operations Plans'' || || || ''Kantor Jeff'' || ||''Completed analysis and cost impact of several operations descope scenarios'' ||''20110520'' || 
    9393|| Update DM parts of LSST System Integration Test Plan  || 20101022 || 20110429 || Allsman Robyn[30%],Freemon Mike[10%],Kantor Jeff[5%] || 0% ||  || 20110421 ||