wiki:MSEReport20110315

Version 4 (modified by robyn, 9 years ago) (diff)

--

Table of Contents

  1. Other Activity

Previous month PT1.2 - Mgt/SE

Current month PT1.2

Next month PT1.2 - Mgt/SE

Note: Please place an asterisk (*) after the percent if you updated this value in this report.

Task Start Finish Resources (lead first) % Complete Comments Last Updated
LSST DMS System Engineering, Proposal, Review Support 20050901 20130405 65%
Prepare and conduct Preliminary Design Review 20080501 20110701 56%
Database and Data Access Analyses Becla Jacek
Scalability tests phase III (up to 250 nodes) 20110303 20110331 Becla Jacek[10%],Wang Daniel[75%],Dubois-Felsmann Gregory[5%] 0%
SSD Database Tests 20100802 20110224 Becla Jacek 95% Still need to finalize the summary document 20101020
Improve trac db documentation for PDR 20090902 20110406 Becla Jacek[10%] 60% 20101018
Write design document for PDR 20110406 20110504 Becla Jacek[5%],Lim KT[5%],Hanushevsky Andy[20%] 0%
Pipeline Middleware Analyses 20110222 20110411 Lim KT[0%],Plante Ray[0%] 0%
Pipeline Execution Middleware Scaling Tests 20110222 20110411 0%
Define scaling tests 20110222 20110228 Plante Ray[5%] 0%
Create benchmark stage implementations and pipeline configurations 20110301 20110321 Daues Greg[25%] 0%
Execute scaling tests, analzye, report results 20110322 20110411 Daues Greg[25%] 0%
Pipeline Execution Monitoring Visualization Tool 20110222 20110404 Plante Ray[25%],Dubois-Felsmann Gregory[25%],Lim KT[25%] 0%
Develop requirements for pipeline processing visualization tool 20110222 20110228 Plante Ray[5%] 0%
Design/acquire/review pipeline processing visualization tool 20110301 20110321 Plante Ray[5%],Pietrowicz Steve[25%] 0%
Implement pipeline processing visualization tool 20110322 20110404 Pietrowicz Steve[75%] 0%
Demonstrate rescheduling of failed processing 20110222 20110404 0%
Define demonstration of rescheduling of failed processing 20110222 20110228 Plante Ray[5%] 0%
Create simulated worker failure mechanism 20110301 20110314 Pietrowicz Steve[50%] 0%
Enable detection of failure and mapping to job 20110315 20110321 Pietrowicz Steve[75%] 0%
Enable rescheduling of failed job 20110322 20110404 Pietrowicz Steve[75%] 0%
Create Calibrated Image on-the-Fly from Raw plus Provenance 20110223 20110308 Lim KT[25%] 0%
MOPS Analyses Axelrod Tim
Complete analysis of runs of FindTracklets/LinkTracklets? and OrbFit? driven by simulated DIASources 20081010 20110304 Axelrod Tim[20%],Myers Jonathan[75%] 75% Determined that the number of false tracks returned by LinkTracklets can be reduced by several orders of magnitude by use of a cut on prob(chisq) for the fit of the coordinates to quadratics on the sky. Significant numbers of true tracks are eliminated by 20101019
Estimate amount of CPU required for LSST MOPS 20101108 20110311 Axelrod Tim[20%],Myers Jonathan[75%] 50% 20101019
Prototype key algorithms in MOPS design 20101206 20110412 Axelrod Tim[20%],Myers Jonathan[75%] 25%
Determine requirements for FutureMOPS that will satisfy solar system science requirements as sketched out in SRD 20110117 20110419 Axelrod Tim[20%],Myers Jonathan[75%] 50%
Complete DM content in LSR and OSS Dubois-Felsmann Gregory
Update star and galaxy counts 20100908 20110225 Dubois-Felsmann Gregory[5%] 75% Values updated for MREFC resubmission. Awaiting a final MC analysis from Ivezic/Juric? to confirm numbers for PDR. 20101020
Extract values for Data Quality Requirements 20101020 20110225 Dubois-Felsmann Gregory[5%] 75% Still need to do a confirmation pass and update numbers associated with MOPS. 20101020
Review LSR to place under change control 20110225 20110316 Kantor Jeff[5%],Axelrod Tim[5%],Dubois-Felsmann Gregory[5%] 0%
Review OSS to place under change control 20110316 20110425 Kantor Jeff[5%],Axelrod Tim[5%],Dubois-Felsmann Gregory[5%],Allsman Robyn[5%],Plante Ray[5%],Lupton Robert[5%],Becla Jacek[5%],Lambert Ron[5%],Lim KT[5%],Freemon Mike[5%],Connolly Andy[5%],Bosch Jim[5%] 0%
Capture network requirements in SysML model 20110425 20110426 Dubois-Felsmann Gregory[5%] 0%
Capture cyber-security requirements in SysML model 20110426 20110503 Dubois-Felsmann Gregory[5%] 0%
Support establishment of traceability between LSR and OSS 20100901 20110505 Dubois-Felsmann Gregory[15%] 62% Isolated improvements to traceability in conjunction with additions
Establish bounding requirements in SysML for MOPS 20101206 20110318 Dubois-Felsmann Gregory[5%] 50% Was awaiting analysis from Tim which is apparently nearly complete now.
Revise DM-FRS Dubois-Felsmann Gregory
Restate existing quantitative requirements as constraint blocks 20110223 20110224 Dubois-Felsmann Gregory[50%] 0% Needs final review.
Update Structure Model Dubois-Felsmann Gregory
Update Structure Model to match revised WBS 20110223 20110224 Dubois-Felsmann Gregory[50%] 0%
Create DM internal ICD N2 diagram 20110225 20110225 Dubois-Felsmann Gregory[50%] 0%
Update OSS/LSR/FRS/SM traceability 20110502 20110513 Dubois-Felsmann Gregory[0%] 0%
Establish traceability of FRS to OSS (or elsewhere) 20110502 20110506 Dubois-Felsmann Gregory[50%] 0% Isolated improvements to traceability in conjunction with additions 20101020
Update Structure Model - FRS traceability 20110509 20110510 Dubois-Felsmann Gregory[50%] 0%
Review traceability with Tim and Chuck, clean up 20110511 20110513 Dubois-Felsmann Gregory[50%],Axelrod Tim[50%] 0%
Prepare ICDs Dubois-Felsmann Gregory
DM-CCS 20110103 20110317 Dubois-Felsmann Gregory[25%],Marshall Stuart[25%] 40%
DM-TCS 20110309 20110322 Sebag Jacques[50%],Dubois-Felsmann Gregory[50%] 50%
Camera CoDR report review 20110322 20110329 Dubois-Felsmann Gregory 0%
DM-OCS 20110317 20110411 Dubois-Felsmann Gregory[50%],Schumacher German[50%] 44% Need to present to DM and OCS groups
DM-EPO 20110502 20110516 Jacoby Suzanne[50%],Dubois-Felsmann Gregory[20%] 0% DM-EPO session held at AHM; significant progress in engaging larger EPO group in understanding what we need; regular DM-EPO contact initiated
DM-sites 20110516 20110523 Dubois-Felsmann Gregory[50%],Lambert Ron[50%],Barr Jeff[50%] 50%
DM - VAO 20110225 20110602 Plante Ray[5%] 0%
Update App and MW Reference Design for DC3a, DC3b PT1, PT1.1 Allsman Robyn 20110315
Update reference design from DC3a and DC3b model 20100930 20110304 Lim KT[25%],Axelrod Tim[10%],Plante Ray[10%],Allsman Robyn[25%],Dubois-Felsmann Gregory[10%] 100%* Completed February 2011 20110315
Develop Performance Budgets, Timing/Sequence? Diagrams for Alert and Data Release steady state 20101014 20110322 Dubois-Felsmann Gregory[50%],Lim KT[75%] 25%
Update reference design - structure model traceability 20110323 20110325 Dubois-Felsmann Gregory[50%],Kantor Jeff[25%],Allsman Robyn[50%],Lim KT[25%],Plante Ray[25%] 0%
Update Infrastructure Reference Design Freemon Mike
Update Mountain/Base? Network Design 20101022 20110301 Lambert Ron[20%] 50% Updated design to show increase to 100 Gbps midway in operations.
Update Long-Haul Network Acquisition Plans 20101022 20110225 Lambert Ron[5%],Kantor Jeff[5%] 8% Updated to show increase to 40 - 100 Gbps midway in operations and pay for LS - SCL infrastructure build up in MREFC. Started discussion regarding funding SCL - MIA during MREFC with AmLight??.
Update Infrastructure Power, Cooling, Floor Space 20110225 20110308 Lambert Ron[10%],Freemon Mike[10%] 0%
Update Infrastructure Trends Document with our position (e.g. SSD, GPU, Advanced Processor Architecture, Virtual Shared Memory) 20110309 20110405 Freemon Mike[20%],Dubois-Felsmann Gregory[20%],Lim KT[20%] 0%
Update Computing, Storage Reference Design Documentation 20110406 20110503 Freemon Mike[20%] 0%
Enterprise Architect Customizations Leader
Requirements and Design for Science User Interface Van Dyk Schuyler
Draft requirements, get feedback, baseline for review 20110223 20110429 Van Dyk Schuyler[50%],Dubois-Felsmann Gregory[5%],Levine Deborah[50%] 0%
Review with SST, update and re-baseline 20110502 20110513 Van Dyk Schuyler[50%],Dubois-Felsmann Gregory[5%],Levine Deborah[50%] 0%
Integrate into FRS and prepare system requirements change requests to integrate 20110516 20110527 Van Dyk Schuyler[5%],Dubois-Felsmann Gregory[25%],Levine Deborah[5%] 0%
Collate existing (best-of-breed) technology options with requirements 20110411 20110506 Van Dyk Schuyler[50%],Dubois-Felsmann Gregory[5%],Levine Deborah[50%] 0%
Review with SAT, update and re-baseline 20110509 20110520 Van Dyk Schuyler[50%],Dubois-Felsmann Gregory[50%],Levine Deborah[50%] 0%
Update SUI WBS 20110523 20110525 Van Dyk Schuyler[50%],Kantor Jeff[50%] 0%
Develop Apps Roadmap and Data Quality Plan Axelrod Tim
Develop Apps sheet of DM Roadmap 20101125 20110304 Axelrod Tim[10%],Allsman Robyn[10%] 67% App Status sheet developed, need more functional descriptions from Apps team
DM Test Plans Allsman Robyn 5%* 20110315
Draft DM Unit Test documents 20100930 20110301 Allsman Robyn[25%] 50% Updated SDP's DM V&V section to include test implementation responsibility during DC and Construction. NOT YET APPROVED by TCT/SAT/etc. 20101008
Draft DM Integration Test documents 20101014 20110308 Allsman Robyn[25%] 50% Draft is outlined and 75% fleshed out. 20101008
Draft DM System Test documents 20110309 20110311 Allsman Robyn[35%] 0%
Draft DM Acceptance Test documents 20110314 20110325 Allsman Robyn[25%] 0%
Generate Integration Test Cases from DM Ref Design Use Cases/Activities? 20110328 20110401 Allsman Robyn[50%] 0%
Create Performance System Test Cases from DM Subsystem Requirements Constraint Blocks 20110404 20110408 Allsman Robyn[50%] 75%* Reorganized Ref Design UML to simplify creation of I&T Test Statements. Still needs updates for missing Algorithm and WBS blocks in theTestCase description. EA RTML output template is functional. 20110315
Generate Functional Acceptance Test Cases from DM Subsystem Requirements 20110411 20110415 Allsman Robyn[50%] 0%
Update DM Sizing Model Freemon Mike
Update Science workbook and explanation document 20110228 20110304 Dubois-Felsmann Gregory[10%],Axelrod Tim[10%] 0% Numbers and basic requirements updated in expectation of reorganization, final object counts.
Update Technology Trends workbook and explanation document 20110222 20110228 Freemon Mike[20%] 0% Interim update toward MREFC resubmission
Consolidate and update Computing workbook and explanation document 20110222 20110228 Lim KT[20%] 0% Interim update toward MREFC resubmission
Consolidate and update I/O and Storage workbook and explanation document 20110222 20110228 Lim KT[10%],Becla Jacek[10%],Axelrod Tim[10%] 0% Interim update toward MREFC resubmission
Update Network workbook and explanation document, integrate into sizing model sheets 20110222 20110304 Lambert Ron[20%],Freemon Mike[10%] 0% Updated with REUNA being paid in MREFC phase. In discussion with AmLight? for similar for SCL - MIA
Complete DM Inputs to Risk Management, System Integration, Commissioning, and Operations Plans Kantor Jeff
Update DM parts of LSST System Integration Test Plan 20101022 20110307 Allsman Robyn[30%],Freemon Mike[10%],Kantor Jeff[5%] 1%
Contribute DM sections to LSST Risk Management, Commissioning, I&T, and Operations Plans 20100416 20110404 Kantor Jeff[10%],Allsman Robyn[20%],Axelrod Tim[20%],Plante Ray[20%],Freemon Mike[20%],Dubois-Felsmann Gregory[13%] 5%
Get MOUs with resource support/commitment from DM partners 20110223 20110419 Kantor Jeff[5%],Van Dyk Schuyler[5%],Freemon Mike[5%],Becla Jacek[5%],Lupton Robert[5%],Lambert Ron[5%] 0%
System Architecture Team Dubois-Felsmann Gregory
Routine SAT operations 20100409 20110527 Dubois-Felsmann Gregory[0%] 0%
PDR final material preparation Kantor Jeff
Update PMCS II DM FDP project 20110603 20110609 Kantor Jeff[5%],Claver Chuck[5%],Jacoby Suzanne[5%],Krabbendam Victor[5%],Kurita Nadine[5%] 0%
Ensure all documents in docushare updated 20110603 20110608 Kantor Jeff[25%],Axelrod Tim[25%],Plante Ray[25%],Freemon Mike[25%],Dubois-Felsmann Gregory[25%],Allsman Robyn[25%],Becla Jacek[25%],Lim KT[25%] 0%
Create PDR presentations 20110609 20110614 Kantor Jeff[25%],Axelrod Tim[25%],Plante Ray[25%],Freemon Mike[25%],Dubois-Felsmann Gregory[25%],Allsman Robyn[25%],Becla Jacek[25%],Lim KT[25%],Van Dyk Schuyler[25%] 0%
Dry Run DM Presentations 20110615 20110620 Kantor Jeff[25%],Axelrod Tim[25%],Plante Ray[25%],Freemon Mike[25%],Dubois-Felsmann Gregory[25%],Allsman Robyn[25%],Becla Jacek[25%],Lim KT[25%],Van Dyk Schuyler[25%] 0%
Update DM Presentations for Final Version for PDR 20110621 20110624 Kantor Jeff[25%],Axelrod Tim[25%],Plante Ray[25%],Freemon Mike[25%],Dubois-Felsmann Gregory[25%],Allsman Robyn[25%],Becla Jacek[25%],Lim KT[25%] 0%
Conduct Preliminary Design Review 20110627 20110701 Kantor Jeff[80%],Axelrod Tim[80%],Van Dyk Schuyler[80%],Plante Ray[80%],Freemon Mike[80%],Dubois-Felsmann Gregory[80%],Allsman Robyn[80%],Becla Jacek[80%],Lim KT[80%] 0%

Other Activity