wiki:MSEReport111510

Version 18 (modified by dgehrig, 9 years ago) (diff)

--

Table of Contents

  1. Other Activity

Previous month PT1.1 - Mgt/SE

Current month PT1.1

Next month PT1.1 - Mgt/SE

Guide on Reporting Percentage Completed:

For software development tasks:

  • use 0% if the solution is still being designed;
  • use 25% if the solution's design is completed;
  • use 50% if the solution is implemented and tested within the Ticket branch;
  • use 75% if the implementation review is complete, the Ticket branch has been merged onto the Trunk branch, and the Ticket is closed.
  • use 100% if the affected Trunk packages are tagged and released.

For level of effort tasks, use % of effort expended rounded to nearest 5%:

For other tasks, still use these increments, but apply their meaning as best as possible:

  • use 0% if the deliverable is still being designed;
  • use 25% if the deliverable's design is completed;
  • use 50% if the deliverable is implemented awaiting review/approval;
  • use 75% if the deliverable has been reviewed and in revision;
  • use 100% if the deliverable is approved and posted to appropriate repository.

Note: Please place an asterisk (*) after the percent if you updated this value in this report.

Task Start Finish Resources (lead first) % Complete Comments Last Updated
Update DM MREFC Cost Estimates Kantor Jeff
Update UML-based Application, Middleware Estimates 11/12/10 11/19/10 Kantor Jeff 25% Application status sheet started, populated with Alert Production, Data Release Production, Calibration Products Production activities. 11/29/10
Update Application, Middleware Cost Estimate and BOE 11/19/10 11/24/10 Kantor Jeff 0%
SC10 Conference 11/13/10 11/19/10 Kantor Jeff,Freemon Mike, Wang Daniel 100% 11/30/10
Update Infrastructure Cost Estimate and BOE 12/28/10 1/4/11 Freemon Mike[15%] 0% Pending resolution of ForcedSource sizing, discussion focused on reducing columns and compressing data. 11/29/10
Publish Estimates via Primavera Web Export 1/4/11 1/5/11 Kantor Jeff[50%] 0%
Update MREFC Proposal 12/16/10 1/26/11 Kantor Jeff[80%],Axelrod Tim[80%],Van Dyk Schuyler[80%],Plante Ray[80%],Freemon Mike[80%],Dubois-Felsmann Gregory[80%],Allsman Robyn[80%],Becla Jacek[80%],Lim KT[80%] 25% Updated existing DM text and graphics from 2007 proposal. Most remaining updates are pending sizing model update. 11/29/10
Update PMCS II Final Design, Construction, Commissioning Plans Kantor Jeff The LSST Level 1 Milestones Plan was rescheduled based on the anticipated start of NSF MREFC funding in FY14, as well as an updated list of DOE CDx review dates provided by the Camera team. The three subsystem projects are being revised accordingly, with a due date of January 3, 2010 for the new baseline. 11/29/10
Update FDP projects 10/22/10 11/4/10 Kantor Jeff[5%],Claver Chuck[5%],Jacoby Suzanne[5%],Krabbendam Victor[5%],Kurita Nadine[5%] 100% No major updates needed, focus is on MREFC projects. Conducted meetings at SLAC to firm up FY11 funding for DM at SLAC. 10/24/10
Update T&S MREFC Project 10/22/10 12/16/10 Krabbendam Victor[20%] 15% Reviewed current plan with Victor Krabbendam, Bill Gressler. 11/29/10
Update DM MREFC Project 10/22/10 12/16/10 Kantor Jeff[20%] 0%
Update Camera MREFC Project 9/30/10 12/2/10 Kurita Nadine[20%] 25% WBS already exists in LSST PMCS, moved old P5-based plan into sandbox. 10/19/10
Update PMO, EPO MREFC Projects 10/22/10 10/28/10 Kantor Jeff[10%],Krabbendam Victor[10%],Jacoby Suzanne[20%] 50% SJ reports on track. Will review this week. 11/29/10
Update Commissioning MREFC Project 10/22/10 10/28/10 Sweeney Don[10%],Kantor Jeff[10%], Krabbendam Victor[10%],Claver Chuck[20%] 0%
Publish plans via Primavera Web Export 10/22/10 10/22/10 Kantor Jeff[50%] 0%
Database and Data Access Analyses Becla Jacek
XLDB 2010 10/6/10 10/25/10 Becla Jacek,Lim KT 75% Need to write report by 12/31, have first draft 11/29/10
Improve trac db documentation for PDR 9/2/09 11/2/10 Becla Jacek[10%] 60% 10/18/10
Research new db technologies - LOE 5/1/08 11/12/10 Becla Jacek[2%],Lim KT[2%],Hanushevsky Andy[2%] 95% Have very interesting results from Calpont, trying to get permission to publish it. Also working closely with MonetDB team 11/29/10
Interact with sciCollab chairs, refresh list of common queries 12/10/08 10/28/10 Becla Jacek[10%] 90% 11/29/10
Scalability tests phase II (up to 100 nodes) 9/1/10 12/15/10 Wang Daniel 30% Tests on 40 nodes completed and documented at dbQservTesting, implementing and integrating S. Monkewitz's spatial UDFs, writing admin tools, getting ready for 100 node tests 11/30/10
SSD Database Tests 8/2/10 11/1/10 Becla Jacek 95% Tests completed, wrote summary which will be published in Docushare later this week. Test results documented at: SSDtests. 11/29/10
Update data storage and i/o sizing estimates 9/20/10 11/11/10 Becla Jacek[70%],Lim KT[30%] 20% Added ForcedSources to the baseline, discussions about image compression. Tested compression of ForcedSources documented at faintSourceCompression 11/29/10
Write design document for PDR 11/12/10 12/9/10 Becla Jacek[5%],Lim KT[5%],Hanushevsky Andy[20%] 0% 11/29/10
MOPS Analyses Axelrod Tim We quantified the distribution of the number of false tracks found for an image pair as roughly log-normal. This allowed us to estimate the CPU requirements for the current linkTracklets and Orbfit as about 3000 node-years for a year of LSST data. This estimate still has large error bars and is being refined. We have also discovered that the use of collapseTracklets, which combines tracklets that overlap, reduces the number of tracklets by about 4x and the number of resultant tracks by about 10x
Complete analysis of runs of FindTracklets/LinkTracklets? and OrbFit? driven by simulated DIASources 10/10/08 11/24/10 Axelrod Tim[20%],Myers Jonathan[75%] 40% http://www.lsstcorp.org/MOPSwiki/index.php?title=Analysis_results 11/29/10
Estimate amount of CPU required for LSST MOPS 11/8/10 12/6/10 Axelrod Tim[20%],Myers Jonathan[75%] 60% 11/29/10
Prototype key algorithms in MOPS design 12/6/10 1/17/11 Axelrod Tim[20%],Myers Jonathan[75%] 0%
Determine requirements for FutureMOPS that will satisfy solar system science requirements as sketched out in SRD 1/17/11 1/31/11 Axelrod Tim[20%],Myers Jonathan[75%] 0%
Plan R&D program for FutureMOPS 1/31/11 2/7/11 Axelrod Tim[20%],Myers Jonathan[75%] 0%
Complete DM content in OSS Dubois-Felsmann Gregory Virtually all requirements established. Quantitative values in most data quality requirements remain to be filled in. 12/1/10
Extract quantitative requirements text from Sizing Model and Data Quality Requirements Document and Scorecard 8/16/10 10/26/10 Dubois-Felsmann Gregory[5%] 90%* Complete except for latest input from Tim. Quantitative TBDs remain. 12/1/10
Update star and galaxy counts 9/8/10 11/2/10 Dubois-Felsmann Gregory[5%] 50% Feedback from ZI digested, need to write up a justification document for the values I'll put in the model. 10/20/10
Extract values for Data Quality Requirements 10/20/10 11/3/10 Dubois-Felsmann Gregory[5%] 25% Done as far as any actual values were present in the DC3 DQ document, most values still needed from Tim. 10/20/10
Capture network requirements in SysML model 11/3/10 11/4/10 Dubois-Felsmann Gregory[5%] 0%
Capture cyber-security requirements in SysML model 11/4/10 12/2/10 Dubois-Felsmann Gregory[5%] 0%
Support establishment of traceability between LSR and OSS 9/1/10 12/24/10 Dubois-Felsmann Gregory[15%] 25%* Further trace relations added, still need comprehensive pass. 12/1/10
Establish bounding requirements in SysML for MOPS 12/6/10 12/20/10 Dubois-Felsmann Gregory[5%] 0%
Revise DM-FRS Dubois-Felsmann Gregory
Restate existing quantitative requirements as constraint blocks 11/1/10 12/27/10 Dubois-Felsmann Gregory[50%] 50%
Enter requirements and constraint blocks into SysML 9/21/10 12/31/10 Dubois-Felsmann Gregory[50%] 50%
Establish traceability of FRS to OSS (or elsewhere) 9/23/10 1/6/11 Dubois-Felsmann Gregory[50%] 20% Isolated improvements to traceability in conjunction with additions 10/20/10
Review traceability with Tim and Chuck, clean up 1/7/11 1/11/11 Dubois-Felsmann Gregory[50%],Axelrod Tim[50%] 0%
Update Structure Model Dubois-Felsmann Gregory
Revise Structure Model to match SysArch? SysML standards 9/30/10 1/12/11 Dubois-Felsmann Gregory[50%] 25%
Update Structure Model to match revised WBS 11/9/10 1/12/11 Dubois-Felsmann Gregory[50%] 50%
Update Structure Model - FRS traceability 1/12/11 1/14/11 Dubois-Felsmann Gregory[50%] 0%
Prepare ICDs Dubois-Felsmann Gregory
Create DM internal ICD N2 diagram 10/22/10 10/22/10 Dubois-Felsmann Gregory[50%] 50%* Created, reviewed with KTL. Need to circulate to full SAT for review. 12/1/10
DM-SDS 10/4/10 10/29/10 Dubois-Felsmann Gregory[50%],Marshall Stuart[50%] 75% DM-SDS session held at AHM
ADASS 2010 Conference 11/7/10 11/11/10 Dubois-Felsmann Gregory,Becla Jacek,Pierfederici Francesco 0%
DM-EPO 10/31/10 11/19/10 Jacoby Suzanne[50%],Dubois-Felsmann Gregory[20%] 75% DM-EPO session held at AHM; significant progress in engaging larger EPO group in understanding what we need; regular DM-EPO contact initiated
DM-CCS 11/22/10 12/17/10 Dubois-Felsmann Gregory[25%],Marshall Stuart[25%] 60%
SLAC December 2010 Holiday Shutdown/Vacation? 12/20/10 12/31/10 Dubois-Felsmann Gregory,Becla Jacek,Lim KT,Wang Daniel 0%
DM-OCS 12/20/10 1/12/11 Dubois-Felsmann Gregory[50%],Schumacher German[50%] 25%
DM-sites 1/3/11 1/19/11 Dubois-Felsmann Gregory[50%],Lambert Ron[50%],Barr Jeff[50%] 50%
DM-TCS 1/17/11 1/24/11 Sebag Jacques[50%],Dubois-Felsmann Gregory[50%] 30%
Update App and MW Reference Design for DC3a, DC3b PT1, PT1.1 Allsman Robyn 20% Revised DMS Reference model loaded into LSST_SysArch. Timing/Sequence? Diagrams for Alert and Data Release steady state loaded into LSST_SysArch 11/29/10
Update reference design from DC3a and DC3b/PT1 model 9/30/10 10/28/10 Lim KT[10%],Axelrod Tim[10%],Plante Ray[10%],Allsman Robyn[25%],Dubois-Felsmann Gregory[10%] 100% Revised DMS Reference model loaded into LSST_SysArch 11/19/10
Develop Performance Budgets, Timing/Sequence? Diagrams for Alert and Data Release steady state 10/14/10 11/9/10 Dubois-Felsmann Gregory[50%],Lim KT[50%] 40% 10/21/10
Update reference design - structure model traceability 11/9/10 11/12/10 Dubois-Felsmann Gregory[50%],Kantor Jeff[25%],Allsman Robyn[50%],Lim KT[25%],Plante Ray[25%] 0%
Compare DM app framework and middleware to ALMA, other projects 10/22/10 10/28/10 Plante Ray[20%],Lim KT[10%] 25% I have done this study, written up some conclusions, but at the moment, I don't recall where I wrote these; I will look this up. 10/26/2010
Update Infrastructure Reference Design Freemon Mike
Update Mountain/Base? Network Design 10/22/10 11/4/10 Lambert Ron[20%] 50% Updated design to show increase to 100 Gbps midway in operations. 10/24/10
Update Long-Haul Network Acquisition Plans 10/22/10 11/4/10 Lambert Ron[5%],Kantor Jeff[5%] 50% Updated to show increase to 100 Gbps midway in operations. 10/24/10
Update Infrastructure Power, Cooling, Floor Space 11/5/10 11/16/10 Lambert Ron[10%],Freemon Mike[10%] 0%
Infrastructure Trends and our position (e.g. SSD, GPU, Advanced Processor Architecture, Virtual Shared Memory) 10/25/10 12/10/10 Freemon Mike[20%],Dubois-Felsmann Gregory[20%],Lim KT[20%] 8% Began organization of several GPU evaluation efforts at AHM 12/1/2010
Update Computing, Storage Reference Design Documentation 10/22/10 11/18/10 Freemon Mike[20%] 0% completed update to cost estimates 12/1/2010
Enterprise Architect Customizations Dubois-Felsmann Gregory Scope of work and requirements defined. Implementation under way by contractor. 12/1/10
Develop Requirements Id Tool 9/3/10 12/14/10 Bartels Jeff[50%] 50%* SOW and requirements agreed, implementation in progress. 10/24/10
Requirements and Design for Science User Interface 10/1/10 2/28/11 Van Dyk Schuyler 10% req document underway 11/29/10
Prepare for SUI workshop with Science Collaborations, Best-of-Breed UI technologists 1/11/11 1/12/11 Van Dyk Schuyler[50%],Dubois-Felsmann Gregory[25%] 20% preparations underway 11/29/10
Define requirements, integrate into FRS and system requirements 1/13/11 2/9/11 Van Dyk Schuyler[50%],Dubois-Felsmann Gregory[25%] 0% 11/29/10
AAS 217 Seattle SUI Workshop 1/9/11 1/10/11 Kantor Jeff[50%],Van Dyk Schuyler[50%] 50% Workshop scheduled at AAS and agenda circulated. 11/29/10
Develop Apps Roadmap and Data Quality Plan Axelrod Tim
Produce a subset of these DQ metrics which have specified metrics, and to the extent possible, include threshold values that must be met to satisfy DQ requirements. 9/30/10 10/29/10 Axelrod Tim[20%] 25%
Produce detailed list of data produced by DM system that need associated DQ metrics, the type of metric needed for each, and the type of verification that will be employed. 9/30/10 11/4/10 Axelrod Tim[20%] 50% 11/29/10
Iterate the DQ metrics and thresholds with the SST, SC, Sci Collabs, yielding a PDR-final set of DQ metrics 11/4/10 11/25/10 Axelrod Tim[20%] 0%
Develop Apps sheet of DM Roadmap 11/25/10 1/6/11 Axelrod Tim[10%] 0%
DM Test Plans Allsman Robyn Generated first draft of IT Cases; needs document reformatting. 11/29/10
Draft DM Unit Test documents 9/30/10 10/28/10 Allsman Robyn[25%] 50% Updated SDP's DM V&V section to include test implementation responsibility during DC and Construction. NOT YET APPROVED by TCT/SAT/etc. 11/1/10
Draft DM Integration Test documents 10/14/10 11/4/10 Allsman Robyn[25%] 50% Draft is outlined and 75% fleshed out. 11/1/10
Draft DM System Test documents 11/5/10 11/9/10 Allsman Robyn[35%] 0%
Draft DM Acceptance Test documents 11/10/10 11/23/10 Allsman Robyn[25%] 0%
Generate Integration Test Cases from DM Ref Design Use Cases/Activities? 11/24/10 11/30/10 Allsman Robyn[50%] 20% Generated Applications IT Cases; need to implement post-processing reformatter. 11/22/10
Create Performance System Test Cases from DM Subsystem Requirements Constraint Blocks 12/1/10 12/7/10 Allsman Robyn[50%] 0%
Generate Functional Acceptance Test Cases from DM Subsystem Requirements 12/8/10 12/14/10 Allsman Robyn[50%] 0%
Update DM Sizing Model Dubois-Felsmann Gregory Organization of new model and schedule of work agreed. 12/1/10
Reorganize DM Sizing Model into single workbooks for Science, Technology Trends, Computing, Storage, Network 11/22/10 12/14/10 Kantor Jeff[10%],Freemon Mike[10%],Dubois-Felsmann Gregory[10%],Lim KT[10%] 10% Basic structure identified and sheet-to-sheet flow diagram created
Update Science workbook and explanation document 12/14/10 12/21/10 Dubois-Felsmann Gregory[10%],Axelrod Tim[10%] 25%* Draft of workbook begun to support calculations for 11/2010 Board preentation. 12/1/10
Update Technology Trends workbook and explanation document 12/14/10 12/21/10 Freemon Mike[20%] 0% 12/1/2010
Consolidate and update Computing workbook and explanation document 12/21/10 12/28/10 Dubois-Felsmann Gregory[20%] 0%
Consolidate and update Storage workbook and explanation document 12/21/10 12/28/10 Lim KT[10%],Becla Jacek[10%],Axelrod Tim[10%] 0%
Update Network workbook and explanation document 12/21/10 12/23/10 Lambert Ron[20%] 0%
Complete DM Inputs to Risk Management, System Integration, Commissioning, and Operations Plans Kantor Jeff
Update DM parts of LSST System Integration Test Plan 10/22/10 11/4/10 Allsman Robyn[30%],Freemon Mike[10%],Kantor Jeff[5%] 0%
Contribute DM sections to LSST Risk Management, Commissioning, I&T, and Operations Plans 4/16/10 11/26/10 Kantor Jeff[10%],Allsman Robyn[20%],Axelrod Tim[20%],Plante Ray[20%],Freemon Mike[20%],Dubois-Felsmann Gregory[13%] 77%
Get MOUs with resource support/commitment from DM partners 10/22/10 12/16/10 Kantor Jeff[5%],Van Dyk Schuyler[5%],Freemon Mike[5%],Becla Jacek[5%],Lupton Robert[5%],Lambert Ron[5%] 0%
PDR final material preparation Kantor Jeff
Ensure all documents in docushare updated 2/7/11 2/11/11 Kantor Jeff[25%],Axelrod Tim[25%],Plante Ray[25%],Freemon Mike[25%],Dubois-Felsmann Gregory[25%],Allsman Robyn[25%],Becla Jacek[25%],Lim KT[25%] 0%
Create PDR presentations 2/11/11 2/17/11 Kantor Jeff[25%],Axelrod Tim[25%],Plante Ray[25%],Freemon Mike[25%],Dubois-Felsmann Gregory[25%],Allsman Robyn[25%],Becla Jacek[25%],Lim KT[25%] 0%
Dry Run DM Presentations 2/17/11 2/23/11 Kantor Jeff[25%],Axelrod Tim[25%],Plante Ray[25%],Freemon Mike[25%],Dubois-Felsmann Gregory[25%],Allsman Robyn[25%],Becla Jacek[25%],Lim KT[25%] 0%
Update DM Presentations for Final Version for PDR 2/23/11 3/1/11 Kantor Jeff[25%],Axelrod Tim[25%],Plante Ray[25%],Freemon Mike[25%],Dubois-Felsmann Gregory[25%],Allsman Robyn[25%],Becla Jacek[25%],Lim KT[25%] 0%
Conduct Preliminary Design Review 5/16/11 5/20/11 Kantor Jeff[80%],Axelrod Tim[80%],Van Dyk Schuyler[80%],Plante Ray[80%],Freemon Mike[80%],Dubois-Felsmann Gregory[80%],Allsman Robyn[80%],Becla Jacek[80%],Lim KT[80%] 0%

Other Activity