Guide on Reporting Percentage Completed:

For all tasks

  • use 0% if the deliverable is still being designed;
  • use 25% if the deliverable's design is completed;
  • use 50% if the deliverable is implemented awaiting review/approval;
  • use 75% if the deliverable has been reviewed and in revision;
  • use 100% if the deliverable is approved and posted to appropriate repository.

Note: Please place an asterisk (*) after the percent if you updated this value in this report.

Management and System Engineering Status Report for August 15, 2010

Allsman Robyn

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE32175%Create document templates, recipes, tools for Enterprise Architect output/generation3/12/094/22/09
MSE21727%Clean up DC3 UML Model, Update LSST Reference Design UML Model from DC3 Model, re-establish traceability to SysML12/1/089/30/10
MSE38450%Generate test cases3/19/0910/1/10
MSE2200%Update DMS Integration and Test Plan 10/1/1010/21/10not started
MSE1534%Contribute DM sections to LSST Risk Management, Commissioning, I&T, and Operations Plans3/23/0910/28/10
MSE1540%Ensure all documents in docushare updated11/23/101/4/11not started
MSE1360%Conduct Preliminary Design Review3/1/113/8/11not started

*Percent updated in this report

Comments:

Other Activities

Axelrod Tim

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE4390%Add crosstalk correction to MOPHOT pipeline4/6/104/12/10not started
MSE44050%Add new subclass to photometry, rework meas10/29/094/22/10
MSE4620%Incorporate Camera Geometry into MOPHOT4/22/104/23/10not started
MSE4420%Persist FOV exposures to MEF4/2/104/5/10not started
MSE4440%Run the 4m data, analyze, report results4/22/104/29/10not started
MSE4320%Run ported algorithm9/16/109/22/10not started
MSE4330%Collect metrics, assess9/23/109/27/10not started
MSE4340%Report scalability results9/27/1010/4/10not started
MSE20717%Update DM system and subsystem functional requirements in SysML12/1/084/12/10
MSE3950%Update Traceability to SRD4/12/105/17/10not started
MSE20975%Update PDR DM - Camera SDS ICDs (Data Control)2/9/094/8/10
MSE21025%Create PDR DM - OCS E&F Database ICD3/12/094/14/10
MSE2110%Create PDR DM - EPO interface requirements3/19/094/14/10not started
MSE31783%Review FRS and ICDs and update with traceability3/5/093/9/09
MSE21727%Clean up DC3 UML Model, Update LSST Reference Design UML Model from DC3 Model, re-establish traceability to SysML12/1/089/30/10
MSE32750%Compare DM app framework and middleware to ALMA, other projects9/29/094/6/10
MSE3180%Review DM Reference Design and update10/1/1010/5/10not started
MSE1534%Contribute DM sections to LSST Risk Management, Commissioning, I&T, and Operations Plans3/23/0910/28/10
MSE1540%Ensure all documents in docushare updated11/23/101/4/11not started
MSE1360%Conduct Preliminary Design Review3/1/113/8/11not started

*Percent updated in this report

Comments:

Other Activities

Baker Bill

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE2145%Update Cyber-security Plan2/9/094/8/10

*Percent updated in this report

Comments:

Other Activities

Bartels Jeff

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE4540%Develop and Test Reverse Engineering De-clutterer4/2/104/29/10not started
MSE4550%Integrate Thread Generator with EA 8 Scenario Generator4/30/105/27/10not started

*Percent updated in this report

Comments:

Other Activities

Becla Jacek

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE33160%Improve trac db documentation for PDR9/2/094/19/10
MSE34775%Interact with sciCollab chairs, refresh list of common queries12/10/084/7/10
MSE34885%Research new db technologies - LOE5/1/086/3/10
MSE38575%Write design document for PDR9/29/094/7/10
MSE39725%Update data storage and i/o sizing estimates11/30/0910/12/10
MSE3180%Review DM Reference Design and update10/1/1010/5/10not started
MSE1540%Ensure all documents in docushare updated11/23/101/4/11not started
MSE1360%Conduct Preliminary Design Review3/1/113/8/11not started

*Percent updated in this report

Comments:

Other Activities

Claver Chuck

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE31783%Review FRS and ICDs and update with traceability3/5/093/9/09
MSE32175%Create document templates, recipes, tools for Enterprise Architect output/generation3/12/094/22/09

*Percent updated in this report

Comments:

Other Activities

Cutri Roc

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE20717%Update DM system and subsystem functional requirements in SysML12/1/084/12/10
MSE31783%Review FRS and ICDs and update with traceability3/5/093/9/09
MSE3180%Review DM Reference Design and update10/1/1010/5/10not started
MSE1534%Contribute DM sections to LSST Risk Management, Commissioning, I&T, and Operations Plans3/23/0910/28/10
MSE1540%Ensure all documents in docushare updated11/23/101/4/11not started
MSE1360%Conduct Preliminary Design Review3/1/113/8/11not started

*Percent updated in this report

Comments:

Other Activities

Dodd Suzanne

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE2200%Update DMS Integration and Test Plan 10/1/1010/21/10not started
MSE1534%Contribute DM sections to LSST Risk Management, Commissioning, I&T, and Operations Plans3/23/0910/28/10
MSE38625%Get letters of resource support/commitment from DM partners12/25/0911/18/10
MSE1540%Ensure all documents in docushare updated11/23/101/4/11not started
MSE1360%Conduct Preliminary Design Review3/1/113/8/11not started

*Percent updated in this report

Comments:

Other Activities

Dubois-Felsmann Gregory

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE4270%Identify hardward platform8/2/108/13/10not started
MSE4330%Collect metrics, assess9/23/109/27/10not started
MSE4340%Report scalability results9/27/1010/4/10not started
MSE20717%Update DM system and subsystem functional requirements in SysML12/1/084/12/10
MSE3950%Update Traceability to SRD4/12/105/17/10not started
MSE20975%Update PDR DM - Camera SDS ICDs (Data Control)2/9/094/8/10
MSE21025%Create PDR DM - OCS E&F Database ICD3/12/094/14/10
MSE2110%Create PDR DM - EPO interface requirements3/19/094/14/10not started
MSE31783%Review FRS and ICDs and update with traceability3/5/093/9/09
MSE21727%Clean up DC3 UML Model, Update LSST Reference Design UML Model from DC3 Model, re-establish traceability to SysML12/1/089/30/10
MSE3180%Review DM Reference Design and update10/1/1010/5/10not started
MSE1534%Contribute DM sections to LSST Risk Management, Commissioning, I&T, and Operations Plans3/23/0910/28/10
MSE1540%Ensure all documents in docushare updated11/23/101/4/11not started
MSE1360%Conduct Preliminary Design Review3/1/113/8/11not started

*Percent updated in this report

Comments:

Other Activities

Ephibian

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE2145%Update Cyber-security Plan2/9/094/8/10

*Percent updated in this report

Comments:

Other Activities

Freemon Mike

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE2200%Update DMS Integration and Test Plan 10/1/1010/21/10not started
MSE1534%Contribute DM sections to LSST Risk Management, Commissioning, I&T, and Operations Plans3/23/0910/28/10
MSE38625%Get letters of resource support/commitment from DM partners12/25/0911/18/10
MSE1540%Ensure all documents in docushare updated11/23/101/4/11not started
MSE1360%Conduct Preliminary Design Review3/1/113/8/11not started

*Percent updated in this report

Comments:

Other Activities

Hanushevsky Andy

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE34885%Research new db technologies - LOE5/1/086/3/10
MSE38575%Write design document for PDR9/29/094/7/10

*Percent updated in this report

Comments:

Other Activities

Ivezic Zeljko

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE31783%Review FRS and ICDs and update with traceability3/5/093/9/09

*Percent updated in this report

Comments:

Other Activities

Kantor Jeff

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE20717%Update DM system and subsystem functional requirements in SysML12/1/084/12/10
MSE3950%Update Traceability to SRD4/12/105/17/10not started
MSE20975%Update PDR DM - Camera SDS ICDs (Data Control)2/9/094/8/10
MSE21025%Create PDR DM - OCS E&F Database ICD3/12/094/14/10
MSE31783%Review FRS and ICDs and update with traceability3/5/093/9/09
MSE32175%Create document templates, recipes, tools for Enterprise Architect output/generation3/12/094/22/09
MSE21727%Clean up DC3 UML Model, Update LSST Reference Design UML Model from DC3 Model, re-establish traceability to SysML12/1/089/30/10
MSE3180%Review DM Reference Design and update10/1/1010/5/10not started
MSE40650%Exercise escalated resources/rates import via SDK9/10/094/2/10
MSE4120%Create UDF and global change to calculate base year $ across plan4/2/104/5/10not started
MSE4160%Update PMCS documentation4/2/104/2/10not started
MSE4170%PMCS2 Import requirements4/2/104/6/10not started
MSE2200%Update DMS Integration and Test Plan 10/1/1010/21/10not started
MSE1534%Contribute DM sections to LSST Risk Management, Commissioning, I&T, and Operations Plans3/23/0910/28/10
MSE38625%Get letters of resource support/commitment from DM partners12/25/0911/18/10
MSE1540%Ensure all documents in docushare updated11/23/101/4/11not started
MSE1360%Conduct Preliminary Design Review3/1/113/8/11not started

*Percent updated in this report

Comments:

Other Activities

Lambert Ron

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE2145%Update Cyber-security Plan2/9/094/8/10

*Percent updated in this report

Comments:

Other Activities

Lim KT

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE34885%Research new db technologies - LOE5/1/086/3/10
MSE38575%Write design document for PDR9/29/094/7/10
MSE39725%Update data storage and i/o sizing estimates11/30/0910/12/10
MSE32750%Compare DM app framework and middleware to ALMA, other projects9/29/094/6/10
MSE3180%Review DM Reference Design and update10/1/1010/5/10not started
MSE1540%Ensure all documents in docushare updated11/23/101/4/11not started
MSE1360%Conduct Preliminary Design Review3/1/113/8/11not started

*Percent updated in this report

Comments:

Other Activities

Lupton Robert

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE4260%Identify algorithm for testing7/30/107/30/10not started
0%Evaluate performance of ported algorithm9/13/1010/4/10not started
MSE4300%Determine scope of data9/13/109/14/10not started
MSE4340%Report scalability results9/27/1010/4/10not started
MSE3180%Review DM Reference Design and update10/1/1010/5/10not started

*Percent updated in this report

Comments:

Other Activities

Monkewitz Serge

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE4410%Configure association pipeline for MOPHOT4/2/104/2/10not started

*Percent updated in this report

Comments:

Other Activities

Plante Ray

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE2110%Create PDR DM - EPO interface requirements3/19/094/14/10not started
MSE31783%Review FRS and ICDs and update with traceability3/5/093/9/09
MSE32750%Compare DM app framework and middleware to ALMA, other projects9/29/094/6/10
MSE3870%Complete Dc3a Abe runs up to 15% FPA equivalent4/2/104/22/10not started
MSE3180%Review DM Reference Design and update10/1/1010/5/10not started
MSE1534%Contribute DM sections to LSST Risk Management, Commissioning, I&T, and Operations Plans3/23/0910/28/10
MSE1540%Ensure all documents in docushare updated11/23/101/4/11not started
MSE1360%Conduct Preliminary Design Review3/1/113/8/11not started

*Percent updated in this report

Comments:

Other Activities

Rosenberg Doug

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE21727%Clean up DC3 UML Model, Update LSST Reference Design UML Model from DC3 Model, re-establish traceability to SysML12/1/089/30/10

*Percent updated in this report

Comments:

Other Activities

Schalk Terry

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE31783%Review FRS and ICDs and update with traceability3/5/093/9/09

*Percent updated in this report

Comments:

Other Activities

Strauss Michael

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE31783%Review FRS and ICDs and update with traceability3/5/093/9/09

*Percent updated in this report

Comments:

Other Activities

TBD

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE4280%Perform the initial port8/16/109/10/10not started
0%Evaluate performance of ported algorithm9/13/1010/4/10not started

*Percent updated in this report

Comments:

Other Activities

Tyson Tony

Reported xx/xx/xx

IDPercentTaskStartEndComments
MSE31783%Review FRS and ICDs and update with traceability3/5/093/9/09

*Percent updated in this report

Comments:

Other Activities