Apps Status Report for June 15, 2010

Guide on Reporting Percentage Completed:

For software development tasks,

  • use 0% if the solution is still being designed;
  • use 25% if the solution's design is completed;
  • use 50% if the solution is implemented and tested within the Ticket branch;
  • use 75% if the implementation review is complete, the Ticket branch has been merged onto the Trunk branch, and the Ticket is closed.
  • use 100% if the affected Trunk packages are tagged and released.

For other tasks, still use these increments, but apply their meaning as best as possible.

Note: Please place an asterisk (*) after the percent if you updated this value in this report.

Allsman Robyn

Reported 17 June 2010

IDPercentTaskComments
APP20079%*validate initial integration run successfully completed

*Percent updated in this report

Comments:

  • The lsst cluster pipeline status including orchestration from ISR through SFM has not changed from last month. We still await the handshake necessary to integrate the final sub-pipeline (SrcAssociation?) into the full pipeline.
  • The pipeline on ABE is not integrated with orchestration; the hand-orchestrated SST pipeline from ISR to SFM is operational on ABE.

Other Activities

  • In preparation of resuming source standards verification,the LSST environment on the Parasoft host system was rebuilt.
  • The upgrade to Enterprise Architect 8.0 permitted the inclusion of Jeff Bartel's new LSST tools supporting automatic generation of integration test descriptions from use cases and activity diagram, and supporting automatic simplification of reverse engineered logical diagrams. Exercising the new LSST tools has uncovered an Enterprise Architect bug. A (tedious) workaround was developed.
  • Two weeks of vacation was also much appreciated.

Axelrod Tim

Reported xx/xx/xx

IDPercentTaskComments
APP1550%photometric self calibrationnot started
APP5680%defining units
APP26120%create calibration catalogs for CFHTLS
APP2910%create input data for ImSimnot started
APP26350%identify set of images for compression tests
APP26090%define DC3b data quality requirements
APP2040%identify scientists to analyze stage outputnot started
APP1990%PT1 best efforts science data analysis/validation not started
APP19150%Provide special case simulation needs (Axelrod)

*Percent updated in this report

Comments:

Other Activities

Becker Andy

Reported xx/xx/xx

IDPercentTaskComments
APP24625%update Diff-Im post design review (ticket 1176)
APP24525%implement correlation function for spatial kernal fit (ticket 1140)
APP1000%test difference imaging coaddsnot started
APP24740%code to measure quality of difference imaging coadds
APP1230%find CFHT fringe frames and move to NCSAnot started

*Percent updated in this report

Comments:

Other Activities

Becla Jacek

Reported 06/18/10

IDPercentTaskComments
APP5450%schema updates for all exposure related tables
APP550%synthetic sources of datanot started
APP5680%defining units

*Percent updated in this report

Comments:

See middleware report

Other Activities

Bickerton Steve

Reported xx/xx/xx

IDPercentTaskComments
APP29525%stellar photometry
APP2560%compute statistics on a sky pixel masked imagenot started

*Percent updated in this report

Comments:

Other Activities

Dubcovsky Martin

Reported 06/17/10

APP108100%*implement convolved Sersic modelsDone
APP11875%*implement multifit pipeline which leverages multifit API and image access frameworkwaiting on resolutions of issues in image acess
APP11975%*implement pipeline stage for extracting ellipse parameters, flux, and bounding box from detectionsAll C++ code for this stage done
APP117100%*implement constrained models for forced photometry Done
APP11610%*create LSST stages for photometryAll C++ code for this stage done

*Percent updated in this report

Comments:

Other Activities

Good John

Reported xx/xx/xx

IDPercentTaskComments
APP2260%code PT1 SUI toolsnot started

*Percent updated in this report

Comments:

Other Activities

Jarvis Mike

Reported 06/17/01

IDPercentTaskComments
APP10550%PSF for deep detection

*Percent updated in this report

Comments:

Other Activities

Jones Lynne

Reported xx/xx/xx

IDPercentTaskComments

*Percent updated in this report

Comments:

Other Activities

Krughoff Simon

Reported 06/18/2010

IDPercentTaskComments
APP840%apply fringe frame correctionnot started
APP83*100%develop camera state classes (CCDinfo and Ampinfo) With RHL's camera geometry classes, I think this is no longer needed
APP82*100%develop calibration products database classes KTL's butler classes do this job
APP253*100%implement ccd assembly code with appropriate stage code
APP252*100%test camera geometry classess with ImSim LSST focal plane model
APP25118%implement datarel.IsrStageUnit? Test
APP250*100%write stage dictionaries and unit tests for ValidateMetaData? and CalibrationDataProducts? There is no longer a validate metadata stage
APP249*100%create policy files for ImSim camera geometry
APP254*100%move saturation and defect correction to the CCD assembly stage

*Percent updated in this report

Comments:

Other Activities

Laher Russ

Reported 6/18/10

IDPercentTaskComments
APP9025%*implement SDQA tool functionality to support DC3b goalsThoth, v. 0.3 is available
APP8925%*query metadata and package in C++ containerISR harvester stage at AMP and CCD levels are in PT1
APP880%implement threshold comparisionnot started
APP21150%WCS verification code
APP21075%ATpy evaluation
APP28325%*identify existing sdqa metricsGot list of ISR metrics from Simon
APP2820%code to validate ISR pipeline outputsnot started
APP2815%*code to validate IC pipeline outputsWrote C code to locate cosmic-ray pixels in ImSim images; sent source code to RHL
APP2800%code to validate image subtractionnot started
APP2880%code to validate detection of sources in subtracted imagenot started
APP2900%code to validate association pipelinenot started
APP2870%code to validate deep detection and measurement pipelinenot started

*Percent updated in this report

Comments:

Other Activities

Trac tickets #1308 and #1310 implemented. Worked on ant build script for Thoth.

Levine Deborah

Reported 06/18/10

IDPercentTaskComments
APP900%implement SDQA tool functionality to support DC3b goalsnot started
APP22985%identify tools to support PT1 data analysis
APP22750%manage PT1 data access tools tasknot started
APP2350%design and document SUI in UMLnot started

*Percent updated in this report

Comments: Continue working with John Good on Gator (catalog search tool) interface for PT1. Interface is working and under test by IPAC science staff.

Other Activities

Lim KT

Reported xx/xx/xx

IDPercentTaskComments
APP60%interslice communicationsnot started
APP70%post spatial matching (stretch goal)not started
APP19275%translate overall production into pipeline, stages, and policies

*Percent updated in this report

Comments:

Other Activities

Lupton Robert

Reported xx/xx/xx

IDPercentTaskComments
APP1390%integrate HEALPix into software stacknot started
APP1000%test difference imaging coaddsnot started
APP12150%adapt astrometry code for DC3b use

*Percent updated in this report

Comments:

Other Activities

Mannings Vince

Reported xx/xx/xx

IDPercentTaskComments
APP2350%design and document SUI in UMLnot started

*Percent updated in this report

Comments:

  1. helped with Gator and Thoth testing
  2. prep work for PT1 evaluation

Other Activities

Monet Dave

Reported xx/xx/xx

IDPercentTaskComments
APP12150%adapt astrometry code for DC3b use

*Percent updated in this report

Comments:

Other Activities

Monkewitz Serge

Reported xx/xx/xx

IDPercentTaskComments
APP1440%move applications code out of stage codenot started
APP1620%modify stage code to conform with new MW APInot started
APP2440%implement/wrap OPTICS source clustering algorithmnot started
APP2430%implement Detection/Source? associationnot started
APP60%interslice communicationsnot started
APP70%post spatial matching (stretch goal)not started
APP740%characteriztion of and improvements to association cosmic ray rejection performancenot started

*Percent updated in this report

Comments:

Other Activities

Mullally Fergal

Reported xx/xx/xx

IDPercentTaskComments
APP8660%implement improvements for WCS
APP15160%implement stage structure for support astrometry code

*Percent updated in this report

Comments:

Other Activities

Myers Jon

Reported xx/xx/xx

IDPercentTaskComments
APP14025%integrate MOPS stages with new C++ KD-Tree tools
APP12935%run DayMOPS with solar system model
APP14175%write linkTracklets and unit tests
APP2670%update DayMOPS for new DIASource Tablenot started
APP2660%Fix C-linkTracklets Python bindingsnot started
APP2650% make DIASource the smallest unit of Tracks and MovingObject??not started
APP2640%update DayMOPS to stop using template tablesnot started
APP2700%remove DIASourceForTonight table, pass DIASource on clipboardnot started
APP2690%pass Tracks on clipboard rather than via Tracks tablenot started
APP2680%made a new initial stage which gets night numbers from Policynot started
APP2710%add debug printing to C find/linkTracklets and stage code for storingnot started

*Percent updated in this report

Comments:

Other Activities

Owen Russell

Reported 6/18/2010

IDPercentTaskComments
APP77100%fix ticket #873
APP1390%integrate HEALPix into software stacknot started
APP9425%code to warp images to/from sky pixel representation
APP20950%implement outlier rejection
APP9850%code to create PSF-matched difference imaging coadds (no outlier rejection)
APP25750%code to create deep monochromatic coadds
APP10475%code to detect chi-squared deep detection coadds (no outlier rejection)
APP1030%create a set of chi-squared deep detection coaddsnot started
APP1020%code to measure quality of deep detection coaddsnot started

*Percent updated in this report

Comments:

Other Activities

Pierfederici Francesco

Reported xx/xx/xx

IDPercentTaskComments

*Percent updated in this report

Comments:

Other Activities

Shaw Dick

Reported 6/18/2010

IDPercentTaskComments
APP240*20%DC3b User Guide
APP2420%create uesr training programnot started
APP2340%develop Use Cases for SUInot started
APP239*100%CFHT-LS Calibration Reference Filesdone
APP208*100%define CFHT to be used"done"

*Percent updated in this report

Comments:

Other Activities

Wrote (w/Co-authors) and submitted a paper on SDQA for the SPIE Astro2010 meeting (7740-18). Drafted PPT slides for SPIE talk.

Van Dyk Schuyler

Reported 06/17/10

IDPercentTaskComments
APP22975%identify tools to support PT1 data analysis
APP2408%DC3b User Guide
APP29650%set up helpdesk systemnot started
APP2340%develop Use Cases for SUInot started
APP2350%design and document SUI in UMLnot started
APP26075%define DC3b data quality requirements
APP23060%complete DM system data product quality metrics document
APP1990%PT1 best efforts science data analysis/validation not started

*Percent updated in this report

Comments:

Other Activities

PT1 analysis/validation plan is 75% done. Ready for PT1 production run data when it comes.

Major Accomplishments

Significant breakthroughs, issues resolved.



Objectives for the Next Period

What you expect to accomplish.



Problems Encountered and Solutions Being Pursued

Budget or schedule variance, technical issues, management issues.