Apps Status Report for March 15, 2010

Guide on Reporting Percentage Completed:

For software development tasks,

  • use 0% if the solution is still being designed;
  • use 25% if the solution's design is completed;
  • use 50% if the solution is implemented and tested within the Ticket branch;
  • use 75% if the implementation review is complete, the Ticket branch has been merged onto the Trunk branch, and the Ticket is closed.
  • use 100% if the affected Trunk packages are tagged and released.

For other tasks, still use these increments, but apply their meaning as best as possible.

Note: Please place an asterisk (*) after the percent if you updated this value in this report.

Allsman Robyn

Reported 16 March 2010

IDPercentTaskComments
APP2040%identify scientists to analyze stage outputnot started - given to TSA
APP2000%validate initial integration run successfully completednot started

*Percent updated in this report

Comments:

Other Activities

DC3b

  • Implementing Buildbot script for nightly pipeline unit testing
  • PT1 Integration and Test Planning

QA Support Tasks

  • (too few) Software Standards check requests
  • testing beta EA 8 for scenario based Activity integration-test generation
  • preparing proposals for the March CCB meeting

SAT Support Tasks

  • Reverse engineered packages to generate logical/class diagrams from implemented code
  • UML design updates resulting from SAT review presentations

Axelrod Tim

Reported xx/xx/xx

IDPercentTaskComments
APP1550%photometric self calibrationnot started
APP1590%evaluate tools and make selectionnot started
APP1580%configure and test for HEALpix projectionnot started
APP1610%configure and test for display of full focal plane LSST imagenot started
APP5650%defining units
APP9180%define DC3b goals for SDQA
APP19150%Provide special case simulation needs (Axelrod)

*Percent updated in this report

Comments:

Other Activities

Becker Andy

Reported 03/15/10

IDPercentTaskComments
APPXX25%Update of ip_diffim based on design review (ticket 1176)*
APPXX25%Implement correlation function for spatial kernel fit (ticket 1140)*
APPXX0%Psf match two models for coadd generation (ticket 1161)*
APP9540%code to measure quality of difference imaging coadds
APP1000%test difference imaging coaddsnot started
APP1230%find CFHT fringe frames and move to NCSAnot started

*Percent updated in this report

Comments:

Other Activities

Becla Jacek

Reported 03/17/10

IDPercentTaskComments
APP53100%*schema updates for all source related tables and object table
APP5410%*schema updates for all exposure related tables
APP550%synthetic sources of datathis is not part of DC3b any more
APP5680%*defining units

*Percent updated in this report

Comments:

Other Activities

see middleware report

Bickerton Steve

Reported xx/xx/xx

IDPercentTaskComments
APP11225%stellar photometry

*Percent updated in this report

Comments:

Other Activities

Bosch Jim

Reported xx/xx/xx

IDPercentTaskComments
APP10875%implement convolved Sersic models
APP1170%implement constrained models for forced photometrynot started
APP1160%create LSST stages for photometrynot started

*Percent updated in this report

Comments:

Other Activities

Cleveland Matt

Reported xx/xx/xx

IDPercentTaskComments
APP1540%develop distributed linkTracklets implementationnot started

*Percent updated in this report

Comments:

Other Activities

Dodd Suzy

Reported 3/15/10

  • Attended Design Reviews: Healpix, Meas_Alg, Pipeline Orchestra, DayMOPS (J. Daily from IPAC/WISE also attended)
  • Attended Seattle breakout meetings on SUI and Data Access. IPAC will lead this new task.
  • Discuss with Mike Freeman and infrastructure WG data access for PT1
  • Start work on coordination of PT1 data access tools. Made inventory of possible IPAC and VO tools.
  • Met with Jeff on IPAC priorities: now- DC3b Science requirements, PT1 data access tools, DC3b User Guide sections: later - Science User Interface use case, requirement generation and documentation.
  • Standard meetings: Apps WG, DC3b, DM management, LSST management

Next Month

  • Finish PT1 data access design and start implementation
  • DC3B plan update
  • Vacation April 12-16

Dubcovsky Martin

Reported 03/16/10

APP10890%*implement convolved Sersic modelsWorking version in trunk. Testing quality of models
APP11850%*implement multifit pipeline which leverages multifit API and image access frameworkAll c++ code for this pipeling exists
APP11925%*implement pipeline stage for extracting ellipse parameters, flux, and bounding box from detectionsAll C++ code for this stage exists
APP11710%*implement constrained models for forced photometryIn design
APP1160%create LSST stages for photometrynot started

*Percent updated in this report

Comments:

Other Activities

Grav Tommy

Reported xx/xx/xx

IDPercentTaskComments
APP1340%generate PS-SSM catalog for LSSTnot started

*Percent updated in this report

Comments:

Other Activities

Jarvis Mike

Reported xx/xx/xx

IDPercentTaskComments
APP10550%PSF for deep detection

*Percent updated in this report

Comments:

Other Activities

Jones Lynne

Reported xx/xx/xx

IDPercentTaskComments

*Percent updated in this report

Comments:

Other Activities

Krughoff Simon

Reported 03/17/2010

IDPercentTaskComments
APP840%apply fringe frame correctionnot started
APP8375%develop camera state classes (CCDinfo and Ampinfo)
APP8225%develop calibration products database classes

*Percent updated in this report

Comments:

Other Activities

Laher Russ

Reported 03/15/10

IDPercentTaskComments
APP900%implement SDQA tool functionality to support DC3b goalsnot started
APP890%query metadata and package in C++ containernot started
APP880%implement threshold comparisionnot started
APP21150%WCS verification stage
APP21075%ATpy evaluation
? 5% WCS failure assessment stage "started"

*Percent updated in this report

Comments:

Other Activities

  • Reviewed my notes from the Tucson meeting in January 2010, and DC3b_Data_Quality_Requirements_V2.pdf.
  • Created detailed SDQA task list for PT1, PT2, and PT3, and sent it to Deborah Levine for review.
  • Started a GWT web application to facilitate DC3b science data validation.
  • Looking at cosmic-rays in ImSim images and their mapping from CCD to amplifier coordinates.

Levine Deborah

Reported 3/15/09

IDPercentTaskComments
APP900%implement SDQA tool functionality to support DC3b goalsnot started

*Percent updated in this report

Comments: This task list really need to be updated per the DC3b replan and my task should probably read "manage" or "coordinate".

  • Updated DC3b plan page
  • Planning an Analysis Support "Implementation Frenzy" in August

Other Activities

  • Still working on SDQA-proper longer range planning
  • Working on solidifying the plan for Data Access Tools and have put tentative tasks into the DC3b plan page. Backend technology and developers have been identified, which front-end tool to use as the model is still under investigation.

Lim KT

Reported xx/xx/xx

IDPercentTaskComments
APP60%interslice communicationsnot started
APP70%post spatial matching (stretch goal)not started
APP1920%translate overall production into pipeline , stages, and policiesnot started

*Percent updated in this report

Comments:

Other Activities

Lupton Robert

Reported xx/xx/xx

IDPercentTaskComments
APP1390%integrate HEALPix into software stacknot started
APP9540%code to measure quality of difference imaging coadds
APP1000%test difference imaging coaddsnot started
APP14980%move applications code out of stage code
APP1670%modify stage code to conform with new MW APInot started
APP10175%simplified background estimation
APP12150%adapt astrometry code for DC3b use

*Percent updated in this report

Comments:

Other Activities

I've been working on:

Definition of HEALPix for LSST. Redesign of meas::algorithms. Porting LSST code to Intel compilers (and os/x 10.6). Managing the P'ton group. Attending phone meetings and design reviews. Other things that I forget.

In other (Subaru) contexts, but relevant to LSST:

Working on file system layouts and objects ("Manager") to encapsulate them

Monet Dave

Reported xx/xx/xx

IDPercentTaskComments
APP12150%adapt astrometry code for DC3b use

*Percent updated in this report

Comments:

Other Activities

Monkewitz Serge

Reported xx/xx/xx

IDPercentTaskComments
APP1440%move applications code out of stage codenot started
APP1620%modify stage code to conform with new MW APInot started
APP60%interslice communicationsnot started
APP70%post spatial matching (stretch goal)not started
APP740%characteriztion of and improvements to association cosmic ray rejection performancenot started

*Percent updated in this report

Comments:

Other Activities

Mullally Fergal

Reported xx/xx/xx

IDPercentTaskComments
APP8660%implement improvements for WCS
APP15125%implement stage structure for support astrometry code

*Percent updated in this report

Comments:

Other Activities

Myers Jon

Reported xx/xx/xx

IDPercentTaskComments
APP14025%integrate MOPS stages with new C++ KD-Tree tools
APP12935%run DayMOPS with solar system model
APP14175%write linkTracklets and unit tests

*Percent updated in this report

Comments:

Other Activities

Owen Russell

Reported xx/xx/xx

IDPercentTaskComments
APP770%fix ticket #873not started
APP940%code to warp images to/from sky pixel representation I had 25% but we switched horses for HEALPix
APP20950%*implement outlier rejection it is likely the final version will operate in HEALPix space
APP9850%code to create PSF-matched difference imaging coadds (no outlier rejection)
APP9540%code to measure quality of difference imaging coadds
APP10450%code to detect chi-squared deep detection coadds (no outlier rejection) further progress awaits HEALPix

*Percent updated in this report

Comments:

Other Activities

Pierfederici Francesco

Reported xx/xx/xx

IDPercentTaskComments

*Percent updated in this report

Comments:

Other Activities

Shaw, Dick

Reported 03/15/10

IDPercentTaskComments
XXX5%Edit new DC3b User GuideConstructed outline, some writing assignments made, created inventory of extant documents
XXX0%Create User training program for analysis of DC3b data productsnot started
XXX*20%Assemble calibration reference files for DC3b processingCreated inventory of CFHT master de-trend files
XXX*10%Compute metric to capture variation of image backgroundimplementation proposal posted to Trac
XXX0%Automate comparison to ground truth for cosmic ray removalnot started
XXX0%Collate and present failure rate statistics for WCS, PSF on selected image typesnot started
XXX0%Generate statistics to characterize the quality of source subtraction in template-subtracted imagesnot started

*Percent updated in this report

Comments:

  • CFHT-LS datasets have been identified for DC3b processing. Results of inventory have been posted to Trac.

Other Activities

  • External User Support
    • Contributed to discussions in Infrastructure WG in planning for user access/support for DC3b data products
  • Planned work
    • Create a Trac page with plan for de-assembling calibration reference files
    • Coordinate w/David Gehrig to transfer calibration reference (a.k.a. de-trend) files from CADC to NCSA.
    • Test scheme for evaluation of background in processed DC3b images

Van Dyk, Schuyler

Reported 3/16/10

  • Attended Design Reviews
  • Initiated work on IPAC-assigned chapters for DC3b User Guide.
  • Attended Seattle meeting on SRD and ImSim, as well as SUI lunch-time breakouts.
  • With Suzy, started work on coordination of PT1 data access tools. Made inventory of possible IPAC and VO tools.
  • Met with Jeff on IPAC priorities.
  • Assumed ownership of DC3b data quality requirements doc and DC3b validation/metrics evaluation tools ("metrics scorecard").
  • Standard meetings: Apps WG, DC3b, TCT, DM management, as well as MW Infrastructure.

TBD

Reported xx/xx/xx

IDPercentTaskComments
APP1030%create a set of chi-squared deep detection coaddsnot started
APP1020%code to measure quality of deep detection coaddsnot started
APP2080%define CFHT to be usednot started
APP2010%identify tools to analyze science data quality of stage outputnot started
APP1990%validate science quality of initial integration runnot started

*Percent updated in this report

Comments:

Other Activities

Major Accomplishments

Significant breakthroughs, issues resolved.



Objectives for the Next Period

What you expect to accomplish.



Problems Encountered and Solutions Being Pursued

Budget or schedule variance, technical issues, management issues.