We will be having our regular bi-weekly Infrastructure WG telecon on Monday, October 26, at 12 Noon CT.
Agenda
- cost sheet change control process / workflow
- http://dev.lsstcorp.org/trac/attachment/wiki/InfrastructureWG/CostSheetChangeControlDiagram.pdf
- main takeaway 1: all cost sheet changes will be managed via tickets
- main takeaway 2: this process will ensure that related documents remain in-sync
- we will be using a more secure ticket system for cost sheet tickets (not trac)
- downside: institution memory of the history of a discussion, admin responsibility for maintaining security, backups, etc.
- mapping document
- https://www.lsstcorp.org/docushare/dsweb/Get/Document-8188/WBSCostMappingDiagram.pdf
- shows how the WBS/MREFC elements relate to the cost sheet elements
- new cost summary with baseline sheet
- https://www.lsstcorp.org/docushare/dsweb/Get/Document-8189/CostSummaryWithBaseline-v62.xls
- motivation: see how the costs change over time as revisions are made to the cost sheet
- main takeaway 1: meaning of cells C3, D3 and row 3 going rightward define "overbudget", "underbudget"
- main takeaway 2: do not panic yet
- Lease (floorspace) does not take into account the increase in drive sizes over time (will decr cost)
- Lease (floorspace) does not include med stor db (will incr cost)
- 3yr step for drives (will decr cost)
- full review (described next)
- etc...
- updated cost sheet
- https://www.lsstcorp.org/docushare/dsweb/Get/Document-6284/Infrastructure-Costs-v62.xls
- major updates include:
- Updated storage estimates to match doc-1779 file version v57 docushare version 60
- Updated Archive site AOS and CSS disk storage
- Updated the Base site med disk requirements
- Updated the DAC site med disk requirements
- Added in a separate line item for controllers with medium disk
- Account for Drive Size Increases Over Time
- Consistently apply 3-year replacement policy for storage
- Add rows showing the 10-year average cost over the survey years
- CommunityAccess tab: Update TF from 45 to 50
- ArchSite AOS Medium Storage: Combine file storage and database storage
- Set leasing costs at Base Site to Zero
- P&C missing for medium storage on ArchAOS, ArchCSS, BaseAOS, BaseCSS, DACCSS
- BaseSite CSS Medium Storage: Split storage into file-based and database-based
- Do not pay maintenance for medium storage that has been replaced
- Change floorspace cost at ArchSite from $136/sf/yr to $175/sf/yr
- Change Power Costs at ArchSite from $0.05/kWh to $0.075/kWh
- Change Power Costs at BaseSite from $0.12/kWh to $0.16/kWh
- next steps with cost sheet
- full review each of the elements of the cost sheet (boxes of the mapping document)
- more readable description of the formulas being used
- identification and documentation of assumptions
- identification and documentation of external data input
- serves two significant purposes
- allows for better internal reviews (validation of models and information used)
- provides justifications for external reviews
- results in an updated (or replacement of) Document-1684 and related documents ("Explanation of Cost Estimates")
- full review each of the elements of the cost sheet (boxes of the mapping document)
- faintsources costs
- summary of current estimates
- more spindles?
- CPU increases?
- storage model costs
- i.e. the cost of going to min. # spindles for CSS database storage to meet performance requirements
- summary of current estimates
- large costs associated with this - need validation from group - error in sheet? revise model? change performance requirements?
Notes
Attendees: JeffK, ChrisC, RayP, K-T, JacekB, GregoryDF, RonL, MikeF
- need to think through how to trigger a baseline update as the cost sheet gets revised (MikeF, JeffK)
- change control, granularity mismatch, signoff, etc.
- update cost sheet to include all elements of the MREFC non-labor infrastructure costs (in order to eliminate "column C" of the cost sheet) (MikeF)
- change terminology in the cost sheet away from "Operations" (MikeF)
- think through the pros/cons of including the (MREFC) development cluster and the integration cluster in these sheets/this process (MikeF)
- MikeF will get direct access to Primavera
- get clarification and revise the faintsources/forcedsources cost estimate (MikeF, with input from Jacek/K-T)
- pushing the discussion on storage model costs (minimum spindle requirements) to the next meeting
- FDP review is Dec15-17