We will be having our regular bi-weekly Infrastructure WG telecon on Monday, October 12, at 12 Noon CT.
Agenda
- Workflow for Cost Estimate spreadsheet request/updates/changes
- Base Site Infrastructure
- Power & Cooling (Ticket #855)
- Power & Cooling costs are current set to be equal. Is this true, or can we improve our model?
- Price per kWh is current set at 5 cents. Should it be 12 cents for Chile? Or something else?
- Lease (Ticket #960)
- Double checking: Lease costs for Base Site are covered by Telescope and Site and should be omitted from DM estimates.
- Power & Cooling (Ticket #855)
- Minimum Spindle Count Requirements (Tickets #942, #943)
- Double checking: For the AOS (both at ArchSite and BaseSite), we don't care about spindle count and only want to optimize for lowest $/TB (for both database and file storage at the AOSs).
- Double checking: Optimizing I/O rates by ensuring a minimum number of spindles only applies to the CSS database storage (not the CSS file storage).
- Double checking: Database sizing is identical for both the ArchCSS and the BaseCSS (specified in Doc 1990).
- DC3b Hardware Requirements
- TG allocations deadlines (Oct 15)
- DC3b schedule (Feb porting; Mar/Apr runs)
- DC3b Hardware Platforms
- DC3b Hardware Requirements
Notes
Attendees: ChrisC, K-T, BillB, Ron Lambert, MikeF
Please correct any errors or omissions directly on this page!
- Base Site Infrastructure
- Power & Cooling (Ticket #855)
- Price per kWh is current set at 5 cents. Should it be 12 cents for Chile? Or something else?
- Power costs will certainly be different in La Serena than in Champaign. InfraWG will morph the cost model. Ticket #855.
- Ron Lambert will provide cost estimates for power in La Serena (today's cost is ~10-12 cents kWh).
- Power & Cooling costs are current set to be equal. Is this true, or can we improve our model?
- The consensus is that we do not have a better ratio to use (ratio of cooling costs to power costs), for either the Base Site or the Arch Site. [Note: This is not a closed issue, but 1-to-1 will continue to be our default for now]
- Price per kWh is current set at 5 cents. Should it be 12 cents for Chile? Or something else?
- Lease (Ticket #960)
- Double checking: Lease costs for Base Site are covered by Telescope and Site and should be omitted from DM estimates.
- Per Ron Lambert, there are no lease costs associated with the Base Site. Updated ticket #960.
- Double checking: Lease costs for Base Site are covered by Telescope and Site and should be omitted from DM estimates.
- Power & Cooling (Ticket #855)
- Minimum Spindle Count Requirements (Tickets #942, #943)
- Double checking: For the AOS (both at ArchSite and BaseSite), we don't care about spindle count and only want to optimize for lowest $/TB (for both database and file storage at the AOSs).
- [Jacek] Yes, that is the current thinking. I can imagine we may be pressed to cut a release in a short period of time, which will put more pressure on disk I/O for database (especially in final stages, like re-partitioning or building indexes)
- Double checking: Optimizing I/O rates by ensuring a minimum number of spindles only applies to the CSS database storage (not the CSS file storage).
- [Jacek] That is what was discussed, but given there are more I/O intensive activities related to file storage that we originally anticipated, this might require rethinking
- Double checking: Database sizing is identical for both the ArchCSS and the BaseCSS (specified in Doc 1990).
- [Jacek] database sizing: yes (images sizing: no)
- Double checking: For the AOS (both at ArchSite and BaseSite), we don't care about spindle count and only want to optimize for lowest $/TB (for both database and file storage at the AOSs).
- DC3b Hardware Requirements
- InfraWG is looking forward to the Tue call, but will assume as a default that 200K SUs is enough.
- Workflow for Cost Estimate spreadsheet request/updates/changes
- The InfraWG is using a new workflow process for cost sheet tracking/changes, and will publish and review during the next call a new Cost Sheet, Workflow Diagram, Cost Summary Comparisons with Baselines, WBS-to-Cost Sheet mappings diagram after a couple of key (external) data elements are verified.